ACTION ITEM
SPONSOR: Teniade Broughton, Chairperson
SUBJECT:
title
DIB WORK PLAN AND REPORT OF ACCOMPLISHMENTS
end
RECOMMENDATION:
recommendation
That the Community Redevelopment Agency approve the Pensacola Downtown Improvement Board (DIB) Fiscal Year 2023 Work Plan.
end
body
SUMMARY:
On September 8, 2020, the Community Redevelopment Agency approved an interlocal agreement with the Pensacola Downtown Improvement Board (DIB) for the implementation of certain Urban Core Redevelopment Plan activities that are funded through the portion of Tax Incremented Financing (“TIF”) revenues derived from the Pensacola Downtown Improvement Taxing District special assessment levied within the DIB area, less $100,000. Under the interlocal agreement the amount retained by the CRA is restricted for implementation of affordable housing initiatives.
Activities authorized for implementation include economic development, marketing, public realm enhancement and beautification, community policing innovations, and supporting the multi-modal enhancement of downtown Pensacola, as authorized by the community redevelopment plan.
Each year, during the CRA’s July meeting, the DIB must present its proposed work plan to the CRA for approval, along with an annual report of the DIB’s accomplishments and activities.
PRIOR ACTION:
July 18, 2005 - the CRA entered into an interlocal agreement with the DIB to provide for the creation of a comprehensive downtown parking strategy and for the implementation of mutual undertakings of the DIB and CRA, as outlined in the Urban Core Community Redevelopment Plan.
September 8, 2020 - The CRA entered into an interlocal agreement with the DIB for the implementation of certain Urban Core Redevelopment Plan activities that are funded through the portion of tax Incremental Financing (“TIF”) revenues derived from the Pensacola Downtown Improvement Taxing District special assessment levied within the DIB area, less $100,000
FUNDING:
Budget: $504,700
Actual: $404,700 Amount to be paid to DIB
$100,000 Affordable Housing Retainage
TOTAL $ 504,700
FINANCIAL IMPACT:
Actual funding provided under the interlocal agreements is based on the property valuation as certified by Escambia County Property Appraiser on July 1, 2022.
LEGAL REVIEW ONLY BY CITY ATTORNEY: Yes
7/6/2022
STAFF CONTACT:
David Forte, Deputy City Administrator - Community Development
Sherry Morris, Development Services Director
M. Helen Gibson, AICP, CRA Manager
Victoria D’Angelo, CRA Assistant Manager
Click or tap here to enter text.
ATTACHMENTS:
1) DIB FY2023 Work Plan
2) DIB Annual Report - 2021 -2022
PRESENTATION: Yes end