That the Community Redevelopment Agency (CRA) award bid #23-027 for construction of Bruce Beach Park Phase 2(B) to Biggs Construction Company, Inc., the lowest and most responsive bidder in the amount of $4,495,446.00 plus a 10% contingency in the amount of $449,545 for a total amount of $4,944,991. Further that the CRA authorize the CRA Chairperson to take all actions necessary to execute the contract.
end
body
SUMMARY:
The Bruce Beach Park improvement project carries out a key component of the 2010 Urban Core Redevelopment Plan, as further conceptualized in the Pensacola Waterfront Framework Plan. The Bruce Beach Park is located at 601 West Main Street, adjacent to South Clubbs Street and west of Maritime Park along Pensacola Bay. The Bruce Beach Park improvement project serves to improve public access to the waterfront and to celebrate the site’s rich history as a former lumber planing mill, dry dock and, most notably, an African American recreation center and swimming pool during segregation.
Invitation to Bid #23-027 was advertised on June 6, 2023 for construction of phase 2B of the park. This phase consists of the construction of connected pedestrian pathways, parking, concrete wall terraces, a mound overlook, a rock scramble, a sand volleyball court, picnic area, and a kayak launch.
Two (2) responsive bids were received. Biggs Construction Company provided the lowest and best responsive bid. The engineer’s cost estimate totaled $3,581,485. The bid amount exceeded the cost estimate by $913,961. Staff recommends covering the overage by drawing from various budgetary line items within the CRA fund, however, it is not anticipated that any projects or programs will be negatively affected by this action. To cover the full cost of the project it is also recommended that funds be drawn from the Series 2017 Urban Core Bond allocation for the A Street Streetscape project and that this project be discontinued at this time.
PRIOR ACTION:
February 10, 20202 - The CRA approved the Bruce Beach Park improvement project for funding through the Urban Core Redevelopment Refunding and Improvement Revenue Bonds, Series 2019.
August 10, 2020 - The CRA approved the Fiscal Year 2021 CRA Work Plan which included the Bruce Beach Park improvement project.
August 9, 2021 - The CRA approved the Fiscal Year 2022 CRA Work Plan which included the Bruce Beach Park improvement project.
May 9, 2022- The CRA awarded Bid No. 22-031 for construction of Bruce Beach Park Phase 1.
February 23, 2023 - The CRA awarded Bid No. 23-008 for Clubbs Street Reconstruction (Bruce Beach Phase 2A)
March 6, 2023 - The CRA was presented the 60% design plans for Bruce Beach Phase 2B.
FUNDING:
Budget: $ 3,769,455 Series 2019 Urban Core Bonds (Bruce Beach)
859,278 Series 2017 Urban Core Bonds (A Street)
300,000 CRA Fund - Sidewalk Repairs
31,645 CRA Fund - Parks and Public Spaces
435,355 CRA Fund - Property Management
190,719 CRA Fund - Commercial Property Improv Pgrm
47,638 CRA Fund - Acquisition & Redevelopment
5,634,090
Actual: $ 315,090 Engineering Design
4,495,446 Construction Contract
449,545 Contingency (10%)
329,759 CEI (Est.)
44,250 Geotechnical (Est.)
5,634,090
FINANCIAL IMPACT:
The total budget for Phase 2B is $5,634,090 which is available within the Series 2019 Urban Core Redevelopment Bonds, the Series 2017 Urban Core Redevelopment Bonds and the CRA fund. To date, $299,996 has been encumbered or expended, leaving a balance of $5,334,094, which is projected to be sufficient to cover the remaining items for this project.
LEGAL REVIEW ONLY BY CITY ATTORNEY: Yes
8/3/2023
STAFF CONTACT:
David Forte, Deputy City Administrator
Sherry Morris, Development Services Director
Victoria D’Angelo, CRA Division Manager
Click or tap here to enter text.
ATTACHMENTS:
1) Bid No. 23-027 Bid Tabulation
2) Final Vendor Reference List
3) Bruce Beach Phase 2 Construction Plans
PRESENTATION: No end