Legislation Details

File #: 23-00599    Version: Name:
Type: Legislative Action Item Status: Passed
File created: 8/3/2023 In control: City Council
On agenda: 8/17/2023 Final action: 8/17/2023
Enactment date: Enactment #:
Title: AWARD OF CONTRACT TO REPLACE (2) TWO HVAC UNITS AT BLUE WAHOOS STADIUM
Sponsors: D.C. Reeves
Attachments: 1. Quote – The Wright Company, 2. Bid Tabulations

LEGISLATIVE ACTION ITEM

 

SPONSOR:                         D.C. Reeves, Mayor

 

SUBJECT:

 

title

AWARD OF CONTRACT TO REPLACE (2) TWO HVAC UNITS AT BLUE WAHOOS STADIUM                     

end

 

RECOMMENDATION:

 

recommendation

That City Council award this contract to The Wright Company, the lowest and best responsible respondent, for a base bid of $130,850 plus 10% contingency in the amount of $13,085 for a total contract price of $143,935. Further, that City Council authorize the Mayor to take the actions necessary to execute and administer this contract and complete this work, consistent with the bid, contracting documents, and the Mayor’s Executive Powers as granted in the City Charter                     

 

end

body                

 

HEARING REQUIRED:  No Hearing Required

 

SUMMARY:

                                          

Two HVAC units at Blue Wahoos Stadium that provide air conditioning to the visiting baseball team’s clubhouse, are inoperable and can’t be repaired. Temporary measures are in place to get through the rest of this baseball season, but long-term fixes must be made as part of Major League Baseball Franchise requirements. Public Works is asking for authorization to select the lowest responsible respondent, from the three quotes obtained by the Blue Wahoos’ Facilities Department. The lead time for the two systems is 16 weeks, thus it is imperative to move forward to make the repairs before the 2024 baseball season.

 

PRIOR ACTION:                     

 

N/A

 

FUNDING:                     

 

     Budget:                     $143,935 CMPA Renewal and Replacement Fund Balance 

 

      Actual:                     $130,850 Construction Cost

                                          $  13,085 Contingency

                                          $143,935 Estimated Cost

 

FINANCIAL IMPACT:

                     

Sufficient funding exists within the Community Maritime Park Management Service Fund to cover this contract.

 

LEGAL REVIEW ONLY BY CITY ATTORNEY:    Yes

 8/4/2023

   

STAFF CONTACT:

 

Kerrith Fiddler, City Administrator

David Forte, Deputy City Administrator

Amy Tootle. Public Works and Facilities Director

 

ATTACHMENTS:

 

1)                     Quote - The Wright Company

2)                     Bid Tabulations

 

PRESENTATION:     No   end