Legislation Details

File #: 23-00713    Version: Name:
Type: Legislative Action Item Status: Passed
File created: 9/12/2023 In control: City Council
On agenda: 10/12/2023 Final action: 10/12/2023
Enactment date: Enactment #:
Title: AWARD OF BID NO. 23-037 CORDOVA SQUARE (MARKETPLACE) AT 12TH AVENUE POND EXPANSION AND REHABILITATION PROJECT
Sponsors: D.C. Reeves
Attachments: 1. Tabulation of Bids, 2. Final Vendor Reference List, 3. Project Location Map

LEGISLATIVE ACTION ITEM

 

SPONSOR:                         D.C. Reeves, Mayor

 

SUBJECT:

 

title

AWARD OF BID NO. 23-037 CORDOVA SQUARE (MARKETPLACE) AT 12TH AVENUE POND EXPANSION AND REHABILITATION PROJECT                     

end

 

RECOMMENDATION:

 

recommendation

That City Council award the contract for Bid No. 23-037 to C.W. Roberts, Inc. of Pensacola, Florida, the lowest and most responsible bidder, with a base bid of $507,448.75, plus a bid alternate amount of $70,875.00, for a total base bid plus bid alternate of $578,323.75, plus a 10% contingency in the amount of $57,832.38 for a total contract price of $636,156.13.  Further, that City Council authorize the Mayor to take the actions necessary to execute and administer this contract and complete the work, consistent with the bid, contracting documents, and the Mayor’s Executive Powers as granted in the City Charter.

end

body                

 

HEARING REQUIRED:  No Hearing Required

 

SUMMARY:

                                          

The purpose of the base bid portion of this project is to mitigate area flooding by excavation to deepen the existing pond located at the northeast corner of 12th Avenue and Marketplace Drive.  The Bid Alternate portion of this project results in the contract removing and replacing the existing chain link fence with new City standard fencing.

 

PRIOR ACTION:                     

 

None

 

FUNDING:                     

 

     Budget:                     $  337,931.43 Stormwater Capital Improvement Fund

                                          $  350,000.00 ARPA Funds

                                          $  687,931.43 Total Funding

 

      Actual:                     $   507,448.75 Base Bid

                                          $      70,875.00 Bid Alternate

                                          $    578,323.75 Base Bid plus Bid Alternate

                                          $      57,832.38 10% Contingency

$      45,500.00 Engineering Management/Inspection (Estimate)

                                          $        1,000.00 Testing/Miscellaneous (Estimate)

                                          $    682,656.13 Total

 

FINANCIAL IMPACT:

                     

Funding has been allocated through the Capital Improvements Fund, as well as ARPA funds, for the Cordova Square Pond Expansion and Rehabilitation project.

 

LEGAL REVIEW ONLY BY CITY ATTORNEY:    Yes

 9/25/2023

   

STAFF CONTACT:

 

Kerrith Fiddler, City Administrator

David Forte, Deputy City Administrator - Community Development

Amy Tootle, PE, Director Public Works & Facilities

Brad Hinote, PE, City Engineer

 

ATTACHMENTS:

 

1)                     Tabulation of Bids

2)                     Final Vendor Reference List

3)                     Project Location Map

 

PRESENTATION:     No   end