City of Pensacola Logo
 
File #: 21-00751    Version: 1 Name:
Type: Legislative Action Item Status: Passed
File created: 8/27/2021 In control: City Council
On agenda: 10/14/2021 Final action: 10/14/2021
Enactment date: Enactment #:
Title: AWARD OF BID #21-037 CROSS STREET, DR MARTIN LUTHER KING JR DRIVE TO 9TH AVENUE DRAINAGE IMPROVEMENTS PROJECT
Sponsors: Grover C. Robinson, IV
Attachments: 1. Bid Tabulation, Bid No. 21-037, 2. Final Vendor Reference List, Bid No. 21-037, 3. Map-Cross Street,Dr. Martin Luther King Jr Drive to 9th Avenue Drainage Improvements Project

LEGISLATIVE ACTION ITEM

 

SPONSOR:                         Grover C. Robinson, IV, Mayor

 

SUBJECT:

 

title

AWARD OF BID #21-037 CROSS STREET, DR MARTIN LUTHER KING JR DRIVE TO 9TH AVENUE DRAINAGE IMPROVEMENTS PROJECT                      

end

 

RECOMMENDATION:

 

recommendation

That City Council award Bid #21-037 Cross Street, Martin Luther King Jr Drive to 9th Avenue Drainage Improvements Project to Site and Utility LLC, of Pensacola Florida, the lowest and most responsible bidder with a base bid of $143,470.00 plus additive alternate #1, in the amount of $52,135.00 plus additive alternate #2, in the amount of $0.00 plus a 10% contingency in the amount of $19,560.50 for a total amount of $215,165.50.  Further, that City Council authorize the Mayor to execute the contract and take all action necessary to complete the project. 

end

body                

 

HEARING REQUIRED:  No Hearing Required

 

SUMMARY:

                                          

The purpose of this project is to provide drainage improvements for Cross Street by installing 5 concrete valley gutters. The portion of Cross Street between MLK and 9th Avenue has standing water issues as a result of a high roadway crown which creates a damming situation. The same scenario exists on Heyward Drive just west of Dunfries Rd. The solution at this location is the installation of 2 concrete valley gutters. This project will mitigate the standing water issues and route water to the nearest positive outfall. The bid alternate portion of this project includes the enlarging of seven curb inlets to effectively move water off the road and into the subsurface piping.

 

PRIOR ACTION:                     

 

None

 

FUNDING:                     

 

     Budget:                     $  252,200.00

 

      Actual:                     $  195,605.00                     Construction Contract - Base Bid

      52,135.00                      Construction Contract - Additive Alternate #1

      19,560.50                      10% Contingency

      21,583.15                      Engineering Design/Permitting/Surveying (Completed)

      10,000.00                      Engineering Management/Inspection (Estimate)

        5,000.00                      Construction Testing/Misc. (Estimate)

$  251,748.65                      TOTAL

 

FINANCIAL IMPACT:

                     

The total budget for this project is $252,200.00 and is funded within the Stormwater Capital Projects Fund.  To date, $21,583.15 has been expended for completed items related to Surveying Engineering Design, Studies, and Permitting, leaving a balance of $230,616.85.  The remaining budget balance is sufficient to cover the remaining items that have yet to be completed/expended.

 

LEGAL REVIEW ONLY BY CITY ATTORNEY:    Choose an item.

 Click here to enter a date.

   

STAFF CONTACT:

 

Kerrith Fiddler, City Administrator

David Forte, Deputy City Administrator - Community Development

Brad Hinote, City Engineer

 

ATTACHMENTS:

 

1)                     Bid Tabulation, Bid No. 21-037

2)                     Final Vendor Reference List, Bid No. 21-037

3)                     Map-Cross Street Dr. Martin Luther King Jr Drive to 9th Avenue Drainage Improvements Project

 

PRESENTATION:     No   end