Title: APPROVAL TO REALLOCATE LOST IV FUNDING FOR THE BAYOU TEXAR BOAT DOCK PROJECT
Sponsors: D.C. Reeves
Attachments: 1. Bid No. 23-012 Tabulation of Bids, 2. Bid No. 23-012 Scope of Work, 3. Bayou Texar Boat Ramp Location Map

LEGISLATIVE ACTION ITEM

 

SPONSOR:                         D.C. Reeves, Mayor

 

SUBJECT:

 

title

APPROVAL TO REALLOCATE LOST IV FUNDING FOR THE BAYOU TEXAR BOAT DOCK PROJECT                     

end

 

RECOMMENDATION:

 

recommendation

That City Council approve the reallocation of funds from LOST IV - East Pensacola Heights to LOST IV - Parks Boat Dock Replacement for the Bayou Texar Boat Dock Project.

end

body                

 

HEARING REQUIRED:  No Hearing Required

 

SUMMARY:

                                          

The purpose of the reallocation of funds is for construction services for the Bayou Texar Boat Ramp Project which needs rehabilitation due to structural deterioration that exceeds repairs.

 

On February 6th, bids were received for the solicitation of construction services relating to the rehabilitation. The lowest and most responsible bid received was $87,432.00 from DKE Marine Services, Inc., a Tier 1 SBE.

 

Partial Funding is available within LOST IV-Parks Boat Dock Replacement in the amount of $75,000.00. The reallocation of funds from LOST IV-East Pensacola Heights in the amount of $29,919.00 will allow to fund the construction service contract and proceed with project.

 

PRIOR ACTION:                     

 

None

 

FUNDING:                     

 

     Budget:                     $   75,000.00 LOST IV Parks Boat Dock Replacement

                                               29,919.00 Reallocation from LOST IV East Pensacola Heights

                                           $104,919.00 Total

 

 

      Actual:                     $ 87,432.00 Contract

                                             17,486.40 20% Contingency

                                          $104,918.40 Total

 

FINANCIAL IMPACT:

                     

Funding is available within the LOST IV fund in the Fiscal Year 2023 Parks and Recreation Budget.

 

LEGAL REVIEW ONLY BY CITY ATTORNEY:    Yes

 2/24/2023

   

STAFF CONTACT:

 

Kerrith Fiddler, City Administrator

David Forte, Deputy City Administrator - Community Development

Adrian Stills, Parks and Recreation Director

Tonya Byrd, Assistant Parks and Recreation Director

 

ATTACHMENTS:

 

1)                     Bid No. 23-012 Tabulation of Bids

2)                     Bid No. Scope of Work

3)                     Bayou Texar Boat Ramp Location Map

 

PRESENTATION:     No   end