City of Pensacola Logo
 
File #: 2022-045    Version: 1 Name:
Type: Resolution Status: Passed
File created: 4/4/2022 In control: City Council
On agenda: 4/14/2022 Final action: 4/14/2022
Enactment date: 4/21/2022 Enactment #: 2022-045
Title: SUPPLEMENTAL BUDGET RESOLUTION NO. 2022-045 - SCHOOL SAFETY IMPROVEMENTS ON COLLEGE PARKWAY
Sponsors: Sherri Myers
Attachments: 1. Supplemental Budget Resolution No. 2022-045, 2. Supplemental Budget Explanation No. 2022-045

LEGISLATIVE ACTION ITEM

 

SPONSOR:                     City Council Member Sherri Myers

 

SUBJECT:

 

title                     

SUPPLEMENTAL BUDGET RESOLUTION NO. 2022-045 - SCHOOL SAFETY IMPROVEMENTS ON COLLEGE PARKWAY                     

end                       

 

RECOMMENDATION:

 

recommendation

That City Council adopt Supplemental Budget Resolution No. 2022-45:

 

A RESOLUTION AUTHORIZING AND MAKING REVISIONS AND APPROPRIATIONS FOR THE FISCAL YEAR ENDING SEPTEMBER 30, 2022; PROVIDING FOR AN EFFECTIVE DATE.

end

body                                                             

 

HEARING REQUIRED:    No Hearing Required      

 

SUMMARY:

 

This item seeks to address school safety concerns regarding pedestrians, particularly students from Washington High School, on College Parkway.  There have been discussions at various times amongst City Council regarding these safety issues and the need for a protective solution.

 

City staff has reviewed the issue and has developed three (3) possible options.  After discussion with staff, it was determined the most efficient and effective solution would be Option 3, however there are complicated issues involved in implementing any of the solutions.

 

The funding request for this item is $150,000, to account for any unforeseen measures that need to be implemented to assure the project meets the needs of the students at Washington High School. It is anticipated that this total amount would not be needed, however through discussions, it was suggested that a bit of funding leeway be included to account for any unforeseen issues that might occur.

 

 

PRIOR ACTION:                     

 

None

 

FUNDING:                     

 

Budget:                     $ 211,463 - LOST IV - Reserves - Capital Equipment

 

                     Actual:                     $150,000 - School Safety Improvements College Parkway (Estimated)

 

 

FINANCIAL IMPACT:

                     

There is currently $211,463 available within the LOST IV Reserves - Capital Equipment.  A reduction of $150,000 for the School Safety Improvements on College Parkway will leave a remainder of $61,463 within the LOST IV Reserves for Capital Equipment.  Adoption of a Supplemental Budget Resolution will appropriate funding for this project.

 

STAFF CONTACT:

 

Don Kraher, Council Executive

 

ATTACHMENTS:

 

1)                     Supplemental Budget Resolution No. 2022-45

2)                     Supplemental Budget Explanation No. 2022-45

 

PRESENTATION:     No