LEGISLATIVE ACTION ITEM
SPONSOR: City Council Member Jared Moore
SUBJECT:
title
BAYVIEW PARK PLAYGROUND FUNDING FOR A POURED IN PLACE BASE VS. ENGINEERED WOOD FIBER.
end
RECOMMENDATION:
recommendation
That City Council allocate $100,000 to the Bayview Park Playground project to allow for a Poured in Place Base.
end
body
HEARING REQUIRED: No Hearing Required
SUMMARY:
On November 18, 2021, City Council approved funding for the Bayview Park Playground. Included within this cost was an Engineered Wood Fiber Base.
Based on previous conversations regarding equitable access to the playground, it is felt that a Poured in Place base would be much more appropriate.
The Poured in Place base has an additional cost of approximately $100,000.
PRIOR ACTION:
November 18, 2021 - City Council approved funding for the purchase of the Bayview Park Playground equipment.
FUNDING:
Budget: $100,000
Actual: $100,000 (Taken from carried forward LOST surplus)
FINANCIAL IMPACT:
Reduction in the LOST surplus that was carried forward of $100,000
STAFF CONTACT:
Don Kraher, Council Executive
ATTACHMENTS:
1) None