Title: PORT OF PENSACOLA - FLORIDA SEAPORT TRANSPORTATION ECONOMIC DEVELOPMENT (FSTED) GRANT #4410272940, VERSION-02 FOR MAINTENANCE DREDGING
Sponsors: Grover C. Robinson, IV
Attachments: 1. Grant Agreement 44102729402

LEGISLATIVE ACTION ITEM

 

SPONSOR:                         Grover C. Robinson, IV, Mayor

 

SUBJECT:

 

title

PORT OF PENSACOLA - FLORIDA SEAPORT TRANSPORTATION ECONOMIC DEVELOPMENT (FSTED) GRANT #4410272940, VERSION-02 FOR MAINTENANCE DREDGING                     

end

 

RECOMMENDATION:

 

recommendation

That City Council authorize the Mayor to execute Public Transportation Grant Agreement (PTGA) 441027294, Version-02 (1st amendment to grant agreement), adding $753,062 in FSTED grant funds to the previously approved and authorized project.

end

body                

 

HEARING REQUIRED:  No Hearing Required

 

SUMMARY:

                                          

On October 11, 2018, City Council authorized the Mayor to accept the FSTED Grant #44102729401 in the total amount of $147,600 for the engineering, design and permitting for the dredging of Port Berths 3 and 5.  At that time, no additional funding was available for the actual dredging to take place.  The City of Pensacola and the Florida Department of Transportation (FDOT) entered into PTGA #4410272940, Version-01 for maintenance dredging at the Port of Pensacola in March 2019.  This 1st amendment to the PTGA will add an additional $753,062 in FSTED funds to the project, requiring $251,020 in additional local match.

 

On May 9, 2013, City Council approved a Joint Participation Agreement between the City and the Florida Department of Transportation for the Berth 6 Rehabilitation Grant for a total amount of $2,600,000.  Since then the City has received three (3) additional supplemental grants for the Berth 6 project.  The Berth 6 Rehabilitation Project has been completed and the final costs were significantly under budget.  The remaining FSTED funds and the Port Matching Grant Funds will be shifted to the Port Berths 3 and 5 dredging project. 

 

Under FSTED program rules, when a project is completed prior to the expiration of the grant with funds remaining in excess of $25,000, the Port to which those funds were allocated can request that the FSTED Council authorize a reallocation of the remaining funds to another approved FSTED project at that Port. The Port of Pensacola made that request at the FSTED Council’s fall meeting last October, and it was approved at that time. The action currently being requested will complete the trailing paperwork required for FDOT to encumber the funds.

 

Both the grant funds and the Port Matching Grant funds for the Berth 6 Rehabilitation will be transferred from the Berth 6 Rehabilitation account to the Berths 3 and 5 Dredging account and the Berth 6 Rehabilitation Phase 1 project will be closed out.

 

PRIOR ACTION:                     

 

May 9, 2013 - City Council adopted a resolution to accept the Joint Participation Agreement between the City and the Florida Department of Transportation for the Berth 6 Rehabilitation grant in the amount of $1,950,000 with a $650,000 required matching funds for a total amount of $2,600,000.

 

October 11, 2018 - City Council authorized the mayor to accept the State of Florida, FSTED Grant #44102729401 in the amount of $110,700 with a $36,900 required matching funds for a total amount of $147,600 for the design, engineering and permitting of the Berths 3 and 5 dredging project.

 

FUNDING:                     

 

     Budget:                     $   110,700                     Berths 3 and 5 Dredging Project

                                                 36,900                     Port Matching Grant Funds Berths 3 and 5 Dredging Project

                                               753,062                     Berth 6 Rehabilitation Project

                                               251,020                     Port Matching Grant Funds Berth 6 Rehabilitation Project

                                          $1,151,682

 

      Actual:                     $   147,600                     Design, Engineering, Permitting, etc.

                                            1,004,082                     Contracting & Dredging

                                          $1,151,682

 

FINANCIAL IMPACT:

                     

Upon approval by City Council, $753,062 from the Berth 6 Rehabilitation Project will be transferred to the Berths 3 and 5 Dredging Project.  Additionally the Port Matching Grant Funds of $251,020 will be transferred from the Berth 6 Rehabilitation Project to the Berths 3 and 5 Dredging Project.  This will allow the Port to fully expend the grant funds previously allocated to the Berth 6 Project which would have expired if not transferred to another approved project. The additional funding will allow for the completion of the dredging project.

 

CITY ATTORNEY REVIEW:    Yes

 4/6/2021

   

STAFF CONTACT:

 

Keith Wilkins, City Administrator

Richard Barker, Jr., Deputy City Administrator - Administration & Enterprise

Amy Miller, Port Director

 

ATTACHMENTS:

 

1)                     Grant Agreement 44102729402

 

PRESENTATION:     No   end