Title: FIRST AMENDMENT TO FLORIDA PUBLIC UTILITIES COMPANY GAS TRANSPORTATION SERVICE AGREEMENT
Sponsors: D.C. Reeves
Attachments: 1. First Amendment To FPU Gas Transportation Service Agreement

LEGISLATIVE ACTION ITEM

 

SPONSOR:                         D.C. Reeves, Mayor

 

SUBJECT:

 

title

FIRST AMENDMENT TO FLORIDA PUBLIC UTILITIES COMPANY GAS TRANSPORTATION SERVICE AGREEMENT                     

end

 

RECOMMENDATION:

 

recommendation

That City Council approve the First Amendment to Florida Public Utilities Company Gas Transportation Service Agreement between the City of Pensacola and Florida Public Utilities (FPU). Further, that City Council authorize the Mayor to take the actions necessary to execute and administer this First Amendment to Florida Public Utilities Company Gas Transportation Service Agreement, consistent with the terms of the agreement and the Mayor’s Executive Powers as granted in the City Charter.

end

body                

 

HEARING REQUIRED:  No Hearing Required

 

SUMMARY:

                                          

In September 2016, Pensacola Energy entered into an agreement with Chesapeake Utilities Corporation d/b/a Florida Public Utilities (FPU) for the construction of the Pensacola Lateral pipeline and Citygate #3.  In 2018, construction was completed and FPU began serving Pensacola Energy with natural gas as a secondary supplier.

 

The purpose of this Amendment is to provide for a second delivery point for natural gas to reinforce Pensacola Energy’s natural gas distribution system serving the north end of Escambia County.  FPU plans to construct a Citygate near Champion Drive and connect to Pensacola Energy’s existing natural gas main.  The term of the original agreement will be extended to 25 years beginning with the in-service date of the new delivery point.

 

PRIOR ACTION:                     

 

None.

 

FUNDING:                     

 

     Budget:                     $176,800

      Actual:                     $176,800

 

FINANCIAL IMPACT:

                     

Gas costs are recovered through the Purchased Gas Adjustment (PGA) component of the gas rate structure.

 

LEGAL REVIEW ONLY BY CITY ATTORNEY:    Yes

 12/29/2022

   

STAFF CONTACT:

 

Kerrith Fiddler, City Administrator

Amy Miller, Deputy City Administrator

Darryl Singleton, Interim Pensacola Energy Director

 

ATTACHMENTS:

 

1)                     First Amendment To FPU Transportation Service Agreement

 