DISCUSSION ITEM
FROM: Grover C. Robinson, IV, Mayor
SUBJECT:
title
ROGER SCOTT TENNIS CENTER - TENNIS COURT IMPROVEMENTS PROJECT
end
body
SUMMARY:
To discuss staff’s alternative recommendations for the Roger Scott Tennis Center - Tennis Court Improvements Project.
PRIOR ACTION:
September 15, 2021 - City Council formally adopted the FY 2022 Budget that included an appropriation of $1,302,545.50 for the renovation of the Roger Scott Tennis Center.
November 18, 2021 - City Council approved an Interlocal Agreement with Escambia County detailing terms for hard court rates, 50/50 funding partnership of the project totaling $1.3M per agency, etc.
July 21, 2022 - City Council awarded a contract to Gulf Coast Tennis Group, LLC. for the operation and management of Roger Scott Tennis Center.
August 18, 2022 - City Council received a presentation regarding revised cost estimates for renovations to Roger Scott Tennis Center along with potential funding sources to assist in offsetting the additional cost.
STAFF CONTACT:
Kerrith Fiddler, City Administrator
David Forte, Deputy City Administrator - Community Development
Adrian Stills, Director - Parks and Recreation Department
ATTACHMENTS:
None
PRESENTATION: No