LEGISLATIVE ACTION ITEM
SPONSOR: Grover C. Robinson, IV, Mayor
SUBJECT:
title
PENSACOLA INTERNATIONAL AIRPORT - STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION PUBLIC TRANSPORTATION GRANT AGREEMENT NO. 435717-7-94-01
end
RECOMMENDATION:
recommendation
That City Council approve the acceptance of the Public Transportation Grant Agreement No. 435717-7-94-01 in the amount of $275,000 to provide partial funding for the construction phase of the rehabilitation of the North half of Taxiway A at the Pensacola International Airport. Further, that City Council approve the grant resolution and authorize the Mayor to take all actions necessary relating to the acceptance and execution of the grant.
end
body
HEARING REQUIRED: No Hearing Required
SUMMARY:
The Florida Department of Transportation (FDOT) Airport Pavement Evaluation Report completed in November 2019 classified the section of Taxiway A between Runway 8-26 and Taxiway A1 as Fair, while Taxiway A1 was classified as Very Poor. In addition to the needs identified in the FDOT Pavement Evaluation Report, the approved Airport Layout Plan (ALP) identified a few geometric improvements along Taxiway A based on Federal Aviation Administration (FAA) requirements.
Under Work Order No. 30, Atkins North America, Inc., will provide an evaluation of the existing conditions, recommendations of pavement rehabilitation methods, and design of airfield pavement improvements. These deliverables are expected to be completed by the end of January 2022. Construction is anticipated to start in May 2022.
This Grant will be used as matching funds to FAA Airport Improvement Program Funding. The balance will be paid from Airport Capital Funds.
PRIOR ACTION:
March 3, 2021 - The Mayor approved Work Order No. 30 with Atkins North America, Inc. for design work related to Taxiway A at the Pensacola International Airport.
FUNDING:
Budget: $ 1,497,590 FAA AIP Grant 47
10,800,000 FY22 FAA Airport Improvement Program Funding
275,000 State of Florida Department of Transportation
925,000 Airport Capital Funds
$13,497,590
Actual: $ 1,497,590 Design
9,600,000 Construction (Estimated)
1,200,000 Contingency (Estimated)
1,200,000 Construction Administration (Estimated)
$13,497,590
FINANCIAL IMPACT:
Funds will be provided from the FDOT on a reimbursable basis.
LEGAL REVIEW ONLY BY CITY ATTORNEY: Yes
1/19/2022
STAFF CONTACT:
Kerrith Fiddler, City Administrator
Amy Miller, Deputy City Administrator - Administration and Finance
Matthew F. Coughlin, Airport Director
ATTACHMENTS:
1) State of Florida Department of Transportation Public Transportation Grant Agreement No. 435717-7-94-01
2) Resolution No. 2022-013
PRESENTATION: No end