File #: 22-00968    Version: 1 Name:
Type: Legislative Action Item Status: Passed
File created: 9/19/2022 In control: City Council
On agenda: 10/13/2022 Final action: 10/13/2022
Enactment date: Enactment #:
Title: AWARD OF BID # 22-048 2022 SIDEWALK PROJECT PHASE 5
Sponsors: Grover C. Robinson, IV
Attachments: 1. Bid Tabulation, Bid No. 22-048, 2. Final Vendor Reference List, Bid No. 22-048, 3. Project Limits-1.pdf, 4. Project Limits-2.pdf

LEGISLATIVE ACTION ITEM

 

SPONSOR:                         Grover C. Robinson, IV, Mayor

 

SUBJECT:

 

title

AWARD OF BID # 22-048 2022 SIDEWALK PROJECT PHASE 5                      

end

 

RECOMMENDATION:

 

recommendation

That City Council approve Award of Bid # 22-048 - 2022 Sidewalk Project Phase 5 to Gulf Beach Construction, Inc. of Gulf Breeze, Florida, the lowest and most responsible bidder with a base bid of $235,757.00, plus a 10% contingency in the amount of $23,575.70 for the total amount of $259,332.70. Further, that City Council authorize the Mayor to execute and administer this contract and complete the work, consistent with the bid, contracting documents, and the Mayor’s Executive Powers as granted in the City Charter.

 

 

end

body                

 

HEARING REQUIRED:  No Hearing Required

 

SUMMARY:

                                          

The purpose of this project is to provide continued ADA-compliant sidewalk connectivity and improve walkability throughout the city. The City website contains the background information related to the methodical process implemented to identify new sidewalk needs throughout the City. Within this same webpage, a list of new sidewalk locations was prioritized, utilizing a standardized prioritization matrix. The locations with the greatest need for new sidewalks received the lowest scores. For the first phase of these new sidewalk projects, the locations identified as having the greatest need, based on the prioritization matrix, were compiled into one set of plans and advertised for bid. Specifically, the project limits for this first phase of new sidewalks are Hart Drive from Fairfax Drive to North 9th Avenue, Fairfax Drive from Hart Drive to E. Fairfield Drive and E. Hernandez Street from Hayne Street to North 9th Avenue.

 

 

PRIOR ACTION:                     

 

None

 

FUNDING:                     

 

     Budget:                     $614,985.13                                          LOST IV   SIDEWALK IMPROVEMENTS

                     

 

 

 

 

      Actual:                     $ 235,757.00                                          Construction Contract- Base Bid

                                          $   23,575.70                                          Required 10% Contingency                     

                                          $   22,500.00           Engineering Management/Inspection (Estimate)

                                          $     1,500.00                                          Testing/Miscellaneous (Estimate)

                                          

                                          $283,332.70                                          Total Needed to Award Project

 

 

 

 

 

FINANCIAL IMPACT:

                     

The total budget for this project is $614,985.13.  City Council previously approved Local Option Sales Tax Series IV funds for sidewalk improvements.

 

LEGAL REVIEW ONLY BY CITY ATTORNEY:    Yes

 9/22/2022

   

STAFF CONTACT:

 

Kerrith Fiddler, City Administrator

 

David Forte, Deputy City Administrator- Community Development

Amy Tootle, Director of Public Works & Facilities

Brad Hinote, City Engineer

 

 

 

 

ATTACHMENTS:

 

1)                     Bid Tabulation, Bid No. 22-048

2)                     Final Vendor Reference List, Bid No. 22-048

3)                     Project Limits-1.pdf

4)                     Project Limits-2.pdf

 

PRESENTATION:     No   end