Title: AMENDMENT TO INTERLOCAL AGREEMENT BETWEEN THE CITY OF PENSACOLA AND ESCAMBIA COUNTY FOR BURGESS ROAD SIDEWALK AND DRAINAGE IMPROVEMENTS PROJECT
Sponsors: Grover C. Robinson, IV
Attachments: 1. Legislative Action Item FILE ID # 21-00206, 2. Interlocal Agreement with Escambia County, 3. Interlocal Agreement with Emerald Coast Utilities Authority, 4. Amendment to Interlocal Agreement with Escambia County

LEGISLATIVE ACTION ITEM

 

SPONSOR:                         Grover C. Robinson, IV, Mayor

 

SUBJECT:

 

title

AMENDMENT TO INTERLOCAL AGREEMENT BETWEEN THE CITY OF PENSACOLA AND ESCAMBIA COUNTY FOR BURGESS ROAD SIDEWALK AND DRAINAGE IMPROVEMENTS PROJECT                      

end

 

RECOMMENDATION:

 

recommendation

That City Council approve the Amendment to the Interlocal Agreement between the City of Pensacola and Escambia County for the Burgess Road Sidewalk and Drainage Improvement Project.

end

body                

 

HEARING REQUIRED:  No Hearing Required

 

SUMMARY:

                                          

Escambia County owns and maintains the right of way along the portion of Burgess Road between Sanders Street and Lanier Drive and originally committed to contribute $500,000.00 for the cost of said portions of the project that lie within the County’s jurisdictional boundaries. The parties wish to amend the Agreement to reflect that the County has committed to contribute up to an additional $35,000 for the cost of said portions of the project that lie within the County’s jurisdictional boundaries as further provided therein.

 

PRIOR ACTION:                     

 

On April 8, 2021, City Council approved the Interlocal Agreement between the City of Pensacola and Escambia County, Florida for Burgess Road Sidewalk and Drainage Improvements Project and Interlocal Agreement between the City of Pensacola and Emerald Coast Utilities Authority, relating to Utility Upgrades as part of the Burgess Road and Drainage Improvements Project.

 

FUNDING:                     

 

     Budget:                     $ 1,640,000.00 Local Option Sales Tax Fund- Burgess Road

                                                200,000.00 Local Option Sales Tax Fund- Sidewalk Improvements

                                                500,000.00 Original Escambia County Interlocal Agreement

                                                200,000.00 Emerald Coast Utilities Authority Agreement

                                                  35,000.00 Amendment #1 Escambia County, Florida contribution

                                          $ 2,575,000.00

 

 

     

Actual:                     $2,039,662.68  Construction Contract

                                               203,966.27  10% Contingency

                                                 35,000.00   Amendment # 1 Escambia County, Florida contribution

                                               209,885.68   Engineering Design/Permitting/Surveying (Completed)

                                                 50,000.00   Engineering Management/Inspection (Estimate)

                                                   8,000.00   Construction Testing/Misc. (Estimate)

                               $ 2,546,514.63

 

 

FINANCIAL IMPACT:

                     

The City has allocated $1,640,000.00 for this project through the Local Option Sales Tax Fund - Burgess Road. In Addition, a budget transfer in the amount of $200,000 will be made within the Local Option Sales Tax Fund moving funding from Sidewalk Improvements to this project. Additional funding in the amount of $700,000 will be reimbursed through Interlocal Agreements with Escambia County and the Emerald Coast Utility Authority., Escambia County will provide $500,000.00 to be used for sidewalk and drainage improvements for those portions of Burgess Road that lie within the County’s jurisdictional boundaries. The modified Agreement will reflect that Escambia County has committed to contribute up to an additional $35,000.00 for the cost of attached said portions of the project that lie within the County’s jurisdictional boundaries as further provided therein. Emerald Coast Utility Authority will provide $200,000 for the cost of utility upgrades that lie within the project’s boundaries.

 

The funding provided through the Escambia County and Emerald Coast Utilities Authority Interlocal Agreements are not reflected in the LOST IV Burgess Road project budget since those cost do not result in an asset to the City.  Instead, as funds related to these Interlocal Agreements are expended, a due from the County or due from ECUA is booked on the City’s general ledger to track the cost.  As reimbursements are received those liability accounts are reduced. 

 

LEGAL REVIEW ONLY BY CITY ATTORNEY:    Yes

 10/17/2022

   

STAFF CONTACT:

 

Kerrith Fiddler, City Administrator

David Forte, Deputy City Administrator- Community Development

Amy Tootle, Director of Public Works & Facilities

Brad Hinote, City Engineer

 

ATTACHMENTS:

 

1)                     Legislative Action Item No. 21-00206 approved 4/2/2021

2)                     Interlocal Agreement with Escambia County