Title: AWARD OF BID NO. 23-021 PENSACOLA INTERNATIONAL AIRPORT TITAN ELEMENT 2 SITE PREPARATION PROJECT
Sponsors: D.C. Reeves
Attachments: 1. ITB No. 23-021 Tabulation of Bids, 2. ITB No. 23-021 Final Vendor Reference List

LEGISLATIVE ACTION ITEM

 

SPONSOR:                         D.C. Reeves, Mayor

 

SUBJECT:

 

title

AWARD OF BID NO. 23-021 PENSACOLA INTERNATIONAL AIRPORT TITAN ELEMENT 2 SITE PREPARATION PROJECT                     

end

 

RECOMMENDATION:

 

recommendation

That City Council award Bid No. 23-021 for Titan Element 2 Site Preparation to HG Construction Development & Investment, Inc. with a base bid of $1,261,500.00 plus 10% contingency of $126,150.00 for a total of $1,387,650.00.  Further, that City Council authorize the Mayor to take the actions necessary to execute and administer the contract and complete the work, consistent with the bid, contracting documents, and the Mayor’s Executive Powers as granted in the City Charter.

end

body                

 

HEARING REQUIRED:  No Hearing Required

 

SUMMARY:

                                          

The City is moving into its final build-out of the planned hangars located at the commercial aircraft maintenance, repair, and overhaul (“MRO”) campus at Pensacola International Airport. The first phase of the campus, known as Project Stallion, consisted of one MRO hangar along with all necessary aircraft aprons and roadways. Hangar 1 achieved completion in the summer of 2018. 

 

The second phase of the MRO campus, known as Project Titian, was broken into two elements.  Element 1 was the construction of the second MRO hangar along with all necessary aircraft aprons and roadways.  Element 1 achieved substantial completion towards the end of calendar year 2022.  Element 2 is the planned construction of two additional hangars (or some form thereof) along with all necessary aircraft aprons and roadways. In an effort to reduce cost and keep the project moving forward, staff broke the scope of work for Element 2 into three separate bid packages: site work, taxiway/apron, and vertical work. 

 

On April 4, 2023, City Purchasing issued Invitation to Bid No. 23-021 for the site preparation of Element 2. Six (6) responses were received and opened on June 8, 2023. HG Construction Development & Investment, Inc. of Miami, Florida, was the lowest and most responsible bidder with a base bid of $1,261,500.00.

 

Funding for the site work is available in the construction line item under Element 2.

 

PRIOR ACTION:                     

 

June 13, 2013 - City Council adopted a resolution to support the acceptance of a grant offered by the Florida Department of Transportation as a Joint Participation Agreement # 43360229401 in the amount of $11,090,000 for Air Commerce Park Phases I and IA - Infrastructure Development.

 

February 13, 2014 - City Council Discussion Item and Presentation on the ST Aerospace Economic Development Project at the Pensacola International Airport.

 

February 27, 2014 - City Council approved the Interlocal Agreement with Escambia County and the City of Pensacola for Funding of Economic Development Project - ST Aerospace of Mobile, Inc.

 

September 9, 2014 - City Council approved the lease with VT Mobile Aerospace Engineering.

 

July 16, 2015 - City Council approved the selection of Greenhut Construction and authorized the Mayor to execute the contract.

 

September 17, 2015 - City Council authorized the Mayor to execute acceptance of the Florida Department of Transportation Joint Participation Agreement # 43571729401 in the amount of $1,531,546 for construction funding to expand the cargo apron and construct a taxiway connector at the Pensacola International Airport of which $1,121,242 will be used towards taxiway connecting future VT MAE facility to runway 17-35.

 

March 17, 2016 - City Council authorized the Mayor to execute acceptance of the Florida Department of Transportation Joint Participation Agreements # 42030029401, # 42960929401, and # 42960939401 in the amount of $2,975,305 for construction of a taxiway connector at the Pensacola International Airport.

 

April 14, 2016 - City Council authorized the Mayor to execute acceptance of the Florida Department of Transportation Joint Participation Agreement # 43571769401 in the amount of $8,599,600 for construction of a hangar at the Pensacola International Airport.

 

September 22, 2016 - City Council authorized the Mayor to execute Amendment No. 1 to the lease the VT Mobile Aerospace Engineering.

 

September 22, 2016 - City Council authorized the Mayor to execute Amendment No. 1 to the contract with Atkins North America.

 

February 8, 2017 - City Council authorized the Mayor to execute Amendment No. 2 and Amendment No. 3 to the contract with Atkins North America.

 

March 8, 2018 - City Council authorized the Mayor to execute acceptance of the State of Florida Department of Economic Opportunity Grant Agreement G0009 in the amount of $4,000,000 for construction of infrastructure related to MRO expansion.

 

September 13, 2018 - City Council authorized the Mayor to accept and execute the State of Florida Department of Transportation Public Transportation Grant Agreement Financial Project 441494-2-94-01 in the amount of $3,000,000 for Pensacola International Airport Facilities Development related to MRO expansion.

 

September 13, 2018 - City Council committed funding in the amount of $10 million from Local Option Sales Tax Series IV in support of the aerospace maintenance repair and overhaul (MRO) campus expansion.

 

February 6, 2019 - City Council approved the amended Interlocal Agreement between the Escambia County Board of County Commissioners and the City of Pensacola related to additional funding requirements for the aerospace maintenance, repair, and overhaul (MRO) campus expansion at the Pensacola International Airport, and approved additional Local Option Sales Tax IV funding of $5 million for the City’s share of the aerospace maintenance, repair, and overhaul (MRO) campus expansion at the Pensacola International Airport.

 

March 28, 2019 - City Council authorized the Mayor to accept and execute the Project Development Agreement, the Master Lease of Real Property, the Triumph Grant Award Agreement, and a State of Florida Dept. of Economic Opportunity Grant in the amount of $10,000,000.

 

August 8, 2019 - City Council authorized the Mayor to accept and execute Financial Award No. 04-79-07378 from the U.S. Department of Commerce, Economic Development Administration in the amount of $12,250,000 for the MRO expansion, and authorized the Mayor to accept and execute State of Florida Dept. of Transportation Amendment to the grant agreement for Financial Project 441494-2-94-01 in the amount of $8,000,000 for the MRO expansion.

 

November 14, 2019 - City Council authorize the Mayor to take all necessary action to execute an Interlocal Agreement for Grant Administration Services for the Economic Development Administration (EDA) Grant #04-79-07378 between the Emerald Coast Regional Planning Council and the City of Pensacola.

 

January 16, 2020 - City Council approved the selection of Brasfield & Gorrie, LLC, as the Construction Manager at Risk for Hangar 2 and authorized the Mayor to execute the contract.

 

March 26, 2020 - City Council authorized the Mayor to execute acceptance of the State of Florida Department of Economic Opportunity Florida Job Growth Infrastructure Grant

Agreement in the amount of $4,875,000 related to the MRO aviation campus expansion project.

 

July 16, 2020 - City Council authorized the Mayor to accept and execute the State of Florida Department. of Transportation Amendment to the grant agreement for Financial Project 441494-2-94-01 in the amount of $34,000,000 for the MRO expansion.

 

August 10, 2020 - City Council approved Resolution 2020-18 related to the State of Florida Department of Transportation Amendment to the grant agreement for Financial Project 441494-2-94-01 in the amount of $34,000,000 for the MRO expansion.

 

November 12, 2020 - City Council approved Amendment No. 1 to Construction Manager At Risk Contact between the City and Brasfield & Gorrie, LLC (The ‘GMP Amendment’) for Hangar 2 of Project Titan/MRO Campus at Pensacola International Airport.

 

August 12, 2021 - City Council authorized the Mayor to accept and execute the State of Florida Department. of Transportation Amendment to the grant agreement for Financial Project 441494-2-94-01 in the amount of $1,000,000 for the MRO expansion.

 

August 18, 2022 - City Council authorized the Mayor to accept and execute the State of Florida Department. of Transportation Amendment to the grant agreement for Financial Project 441494-2-94-01 in the amount of $2,000,000 for the MRO expansion.

 

December 15, 2022 - City Council approved Amendment No. 1 of the Interlocal Agreement between the City of Pensacola and Emerald Coast Regional Planning Council extending the Interlocal through the term of the grant.

 

May 25, 2023 - City Council approved the award of Project Titan Hangar 2 Parking Lot Modifications to Gulf Beach Construction and authorized the Mayor to execute and administer the contract.

 

FUNDING:                     

 

      Budget:                     $   35,000,000   VT MAE

                                               14,000,000   Governor’s Job Growth

                                               48,000,000   FDOT Grant

                                               15,000,000   Escambia County

                                               15,000,000   City Local Option Sales Tax Series IV

                                               12,250,000   Federal - U.S. Economic Development Administration

                                               66,000,000   Triumph Gulf Coast

                                                 4,875,000   Florida DEO Grant

                                          $ 210,125,000

 

                                              Element 1 

      Actual:                     $    2,371,801   Design

                                                   277,645    Design Development Services

                                                1,812,640   Contract Administration Services

                                                   120,560    Cost Estimating Services

                                                3,340,999    FAA Project Funding

                                                2,595,204    Professional Services

                                              15,438,639   Owner Direct Purchases

                                              36,166,135   Construction Manager at Risk  

                                                   117,562   Parking Lot Modifications

                                                   128,319   Miscellaneous (permit fees, eng. alloc., misc.)

                                                   930,496   Contingency

                                          $  63,300,000   Sub-Total Element 1

 

                                               Element 2

$    5,525,000   Design

                                                5,500,000   Construction Administration Services

                                                   403,120   Contract Management Services

                                                   300,000    Facility Commissioning

                                                   879,927    Geotech and Environmental Assessment

                                                1,496,880    Professional Services

                                                   650,000    Bridge Financing

                                                3,375,000   Owners Contingency

                                            128,695,073   Construction

                                          $146,825,000   Sub-Total Element 2

 

$210,125,000   TOTAL FUNDING

 

FINANCIAL IMPACT:

                     

The funds for the project were appropriated in the Airport Fund on Supplemental Budget Resolution No. 2019-13 at the March 28, 2019, City Council Meeting.  The total project cost is being funded by a combination of VT MAE investment, state grants, federal grants, and local funds, as detailed above under “Funding”.  Funding for the site work is available in the construction line item under Element 2.

 

LEGAL REVIEW ONLY BY CITY ATTORNEY:    Yes

 7/26/2023

   

STAFF CONTACT:

 

Kerrith Fiddler, City Administrator

Amy Miller, Deputy City Administrator - Administration & Enterprise

Matthew Coughlin, Airport Director

 

ATTACHMENTS:

 

1)                     ITB No. 23-021 Tabulation of Bids

2)                     ITB No. 23-021 Final Vendor Reference List

 

PRESENTATION:     No   end