City of Pensacola Logo
 
File #: 16-00326    Version: 1 Name:
Type: Legislative Action Item Status: Passed
File created: 12/13/2016 In control: City Council
On agenda: 1/12/2017 Final action: 1/12/2017
Enactment date: Enactment #:
Title: Award of Contract to Caldwell Associates Architects, Inc. for RFQ #16-024 for Architectural and Engineering Services for the Construction of Bayview Community Resource Center.
Sponsors: Ashton J. Hayward, III
Attachments: 1. Fee Proposal.pdf, 2. Tabulation Sheet.pdf, 3. Oral Presentation Ranking Matrix.pdf, 4. Final Vendor Reference List.pdf

LEGISLATIVE ACTION ITEM

 

SPONSOR:                         Ashton J. Hayward, III, Mayor

 

SUBJECT:

 

title

Award of Contract to Caldwell Associates Architects, Inc. for RFQ #16-024 for Architectural and Engineering Services for the Construction of Bayview Community Resource Center.                     

end

 

RECOMMENDATION:

 

recommendation

That City Council award contract to Caldwell Associates Architects, Inc. of Pensacola for RFQ # 16-024 for Architectural and Engineering Services for the Construction of a Community Resource Center at Bayview Park, for an agreed upon fee of 7.00% of construction costs, estimated at $315,828, plus eligible reimbursable expenses and additional services estimated at $404,500, for a total estimated cost of $720,328.  Further, that Council authorize the Mayor to execute all contracts and related documents and take all related actions necessary to complete the project.

end

body                

 

AGENDA:                                          Consent

 

                     Public Hearing Required:                     No Hearing Required

 

SUMMARY:

                                          

On February 11, 2016, Council approved the expenditure of funds in the amount of $9,350,000 for the rebuilding of Fire Station #3 ($3,300,000) and Bayview Community Resource Center ($6,050,000) from the One-Cent Local Government Infrastructure Surtax extension from January 1, 2018 through December 31, 2028 (LOST Series IV). 

 

In April 2016, the City issued a Request for Qualifications (RFQ) for Architectural and Engineering services for the new Bayview Community Resource Center.  Thirteen firms responded to the RFQ.  A selection committee was appointed to review the responses, comprised of 1) Kim Carmody, City of Pensacola Parks and Recreation; 2) Steven Shelly, East Neighborhood Heights Association; 3) Bill Healy, UWF Recreation Department; 4) Juliette Moore, former Recreation Director of the University of Arizona; and 5) Pablo Mirabal, private citizen.

 

The selection committee reviewed the responses and invited the following four firms to make oral presentations: Caldwell Associates Architects, DAG Architects, Quina Grundhoefer Architects, and Bay Designs Associates Architects.  These four top firms made oral presentations to the selection committee on October 24, 2016, and upon completion of the presentations, the committee ranked the firms in the following order:

 

1)                     Caldwell Associates

2)                     DAG Architects

3)                     Quina Grundhoefer Architects

4)                     Bay Design Associates Architects

 

Staff has negotiated a contract with Caldwell Associates and a basic design fee of 7% for this project. This design fee is consistent with the State of Florida A&E Fee Service Schedule recommendation.  The total A&E fee for the Bayview Community Resource Center is a combination of the Design Fee, Additional Services, and Estimated Reimbursable items for the project.

 

 

PRIOR ACTION:                     

 

February 11, 2016 - City Council authorized the funding for the rebuilding of Fire Station #3 and Bayview Resource Center.

 

FUNDING:                     

 

     Budget:                     $6,050,000.00

 

      Actual:                     $4,500,000.00                     Estimated Construction Cost

                                               450,000.00 10% Contingency

                                               315,828.00                     7% Design Fee

                                               404,500.00                     Additional A&E Services and Soft Costs

                                               279,000.00                     Miscellaneous Expenses

                                               100,672.00 Project Management & Inspection

                                          $6,050,000.00                     Total                     

 

 

FINANCIAL IMPACT:

                     

Funding is available in the Local Option Sales Tax Fund.

 

CITY ATTORNEY REVIEW:    Yes

 1/3/2017

   

STAFF CONTACT:

 

Eric W. Olson, City Administrator

Brian Cooper, Parks and Recreation Director

Robbie McGuire, Building Construction and Facilities Manager

George Maiberger, Purchasing Manager

 

ATTACHMENTS:

 

1)                     Fee Proposal

2)                     Tabulation Sheet

3)                     Oral Presentation Ranking Matrix

4)                     Final Vendor Reference List

 

PRESENTATION:     No                        