File #: 17-00049    Version: 1 Name:
Type: Legislative Action Item Status: Passed
File created: 1/23/2017 In control: City Council
On agenda: 2/9/2017 Final action: 2/9/2017
Enactment date: Enactment #:
Title: FY 2017 Street Rehabilitation - Interlocal Agreement with Escambia County
Sponsors: Ashton J. Hayward, III
Attachments: 1. Interlocation agreement between Escambia County Board of County Commisioners and the City of Penscola relating to Road Surfacing

LEGISLATIVE ACTION ITEM

 

SPONSOR:                         Ashton J. Hayward, III, Mayor

 

SUBJECT:

 

title

FY 2017 Street Rehabilitation - Interlocal Agreement with Escambia County                     

end

 

RECOMMENDATION:

 

recommendation

That City Council authorize the Mayor to take all necessary action to execute an Interlocal Agreement with Escambia County to facilitate the re-paving of certain streets on the border of the City/County Limits.

end

body                

 

HEARING REQUIRED:  No Hearing Required

 

SUMMARY:

                                          

On January 12, 2017, City Council approved an action item entitled FY 2017 Street Rehabilitation Group 8 and FY 2017 Street Rehabilitation Group 9. FY 2017 Street Rehabilitation Group 8 contains 204 blocks and Group 9 contains 202 out of a total of 618 blocks that is being performed in the FY 2017 Street Rehabilitation project groups.  Some of these streets are on the border of the City/County jurisdictional limits creating situations where only a portion of a block would be paved within the City limits in order to avoid paving in the County.

 

Public Works & Facilities staff contacted Escambia County with regard to funding assistance as it relates to the paving of the identified blocks that rest at the City/County limits.  Escambia County expressed a desire to have those roadways resurfaced during the City projects.  Currently, the estimate for the County portion that would be added to the re-paving project is approximately $100,000.00 and will be paid for by Escambia County, per the terms of the Interlocal Agreement.

 

PRIOR ACTION:                     

 

January 12, 2017 - City Council approved an action items entitled “FY 2017 Street Rehabilitation Group 8” and FY2017 Street Rehabilitation Group 9”

 

November 17, 2016 - City Council approved an action item entitled “FY 2017 Street Rehabilitation Project List”

 

July 14, 2016 - City Council approved an action item entitled “Six-Cent Local Option Fuel (Gasoline) Tax” to authorize financing not to exceed $15 million for street rehabilitation, street reconstruction and intersection/traffic improvements.

 

FUNDING:                     

 

 Budget:                     $   100,000.00                       Escambia County Interlocal Agreement

                                          

Actual:                                          $   100,000.00   Estimated cost

 

 

FINANCIAL IMPACT:

                     

Escambia County will provide the agreed upon amount of reimbursement to the City as specified in the Interlocal Agreement between both parties.

 

CITY ATTORNEY REVIEW:    Yes

 1/25/2017

   

STAFF CONTACT:

 

Eric W. Olson, City Administrator

L. Derrik Owens, P.E., Director of Public Works and Facilities/City Engineer

 

ATTACHMENTS:

 

1)                     Interlocal Agreement Between Escambia County Board of County Commissioners and the City of Pensacola Relating to Road Resurfacing

 

PRESENTATION:     No   end