City of Pensacola Logo
 
File #: 17-00527    Version: 1 Name:
Type: Legislative Action Item Status: Passed
File created: 9/5/2017 In control: City Council
On agenda: 10/12/2017 Final action: 10/12/2017
Enactment date: Enactment #:
Title: AWARD OF BID# 17-033 - PORT OF PENSACOLA WAREHOUSE #1 MODIFICATION PROJECT
Sponsors: Ashton J. Hayward, III
Attachments: 1. Tabulation Sheet, Bid # 17-033, 2. Vendor Reference Sheet, Bid # 17-030

LEGISLATIVE ACTION ITEM

 

SPONSOR:                         Ashton J. Hayward, III, Mayor

 

SUBJECT:

 

title

AWARD OF BID# 17-033 - PORT OF PENSACOLA WAREHOUSE #1 MODIFICATION PROJECT                     

end

 

RECOMMENDATION:

 

recommendation

That City Council award ITB # 17-033 Port of Pensacola Warehouse #1 Modification to Emerald Coast Constructors Inc., the sole bidder with a base bid of $1,495,383.90 plus a 5% contingency of $74,769.20 for a total amount of $1,570,153.10 Further, that Council authorize the Mayor to execute the contract and take all actions necessary to complete the project.

end

body                

 

HEARING REQUIRED:  No Hearing Required

 

SUMMARY:

                                          

The Port of Pensacola was awarded a State of Florida economic development grant to modify an existing warehouse to install overhead cranes. The contemplated improvements will result in an additional marketable asset for the port.

 

The Warehouse #1 Modification Project consists of the addition of two new overhead bridge cranes and requires the fabrication and erection of a structural steel crane runway system. To accommodate the required lift height for the high bay crane, a portion of the existing warehouse roof will be removed and a new pre-engineered metal building will be installed in the area of the high bay crane.  New foundations and associated demolition will be required to support the metal building frames and the low bay crane runway steel. Electrical upgrades will be required to provide lights for the new high bay area and to provide power for the new bridge cranes.

 

The original grant acceptance approved in early 2013 called for the overhead crane facility improvements to be constructed in Warehouse #9. The original project also included improvements to dockside utility infrastructure (additional shore power and sanitary sewer stations) at Berths 1 and 2, if total project funding was sufficient to do so.

 

Following preliminary geotechnical and engineering work at the Warehouse #9 site, it was determined that this was not a suitable location for the overhead crane facility and the project should be relocated to Warehouse #1. Additionally, early cost estimates indicated that construction of the overhead crane facility, which was the primary project under the grant, would require the entire $2 million in project funding and that construction of the originally-contemplated dockside utility improvements would not be possible. An amendment to the Project Fund Agreement, fully executed between the City and FDOT on June 4, 2015, revised the project scope to document and authorize these changes.

 

PRIOR ACTION:                     

 

June 14, 2012 - Council approved Resolution 23-12, a mid-year supplemental budget resolution appropriating the grant funds into the Port’s capital budget.

 

January 10, 2013 - Council approved Resolution 01-13 formally accepting the grant and authorizing the Mayor to execute all documents necessary thereto.

 

FUNDING:                     

 

Budget:                     $2,000,000                     State of Florida Grant

                                                 17,555                     Port Funding (only if needed for contingency)

Total                                          $2,017,555

 

 

Actual:                                          $   192,817                     Warehouse #9 location engineering

                                                 14,142                     Warehouse #9 location miscellaneous expenses

                                               206,959                     Sub-total Warehouse #9 location expenses

 

                                            1,495,384                     Warehouse #1 location construction bid price

                                                 74,770                     Warehouse #1 location 5% construction contingency

                                               225,442                     Warehouse #1 location A&E contract

                                                   5,000                     Warehouse #1 location Engineering Management (estimated)

                                                 10,000                     Warehouse #1 location miscellaneous expenses (estimated)

                                            1,810,596                     Sub-total Warehouse 1 location expenses

Total                                          $2,017,555

                                          

 

FINANCIAL IMPACT:

                     

Grant funding in the amount of $2,000,000 has been appropriated for this project.  To date, $433,720.92 has been previously expended or is currently encumbered for the project leaving an available balance of $1,566,279.08 to complete the project. Port funding of up to $17,555 will make up any shortfall, should it occur.

 

CITY ATTORNEY REVIEW:    Yes

 9/15/2017

   

STAFF CONTACT:

 

Eric W. Olson, City Administrator

Amy Miller, Port Director

 

ATTACHMENTS:

 

1)                     Tabulation Sheet, Bid # 17-033

2)                     Vendor Reference Sheet, Bid # 17-033

 

PRESENTATION:     No   end