File #: 18-00045    Version: 1 Name:
Type: Legislative Action Item Status: Passed
File created: 1/10/2018 In control: City Council
On agenda: 2/8/2018 Final action: 2/8/2018
Enactment date: Enactment #:
Title: AIRPORT - VT MOBILE AEROSPACE ENGINEERING, INC. PROJECT AT PENSACOLA INTERNATIONAL AIRPORT - AMENDMENT NO. 2 AND AMENDMENT NO. 3 TO ARCHITECTURAL AND ENGINEERING DESIGN SERVICES
Attachments: 1. Amendment No. 2, 2. Amendment No. 3

LEGISLATIVE ACTION ITEM

 

SPONSOR:                         Ashton J. Hayward, III, Mayor

 

SUBJECT:

 

title

AIRPORT - VT MOBILE AEROSPACE ENGINEERING, INC. PROJECT AT PENSACOLA INTERNATIONAL AIRPORT - AMENDMENT NO. 2 AND AMENDMENT NO. 3 TO ARCHITECTURAL AND ENGINEERING DESIGN SERVICES                     

end

 

RECOMMENDATION:

 

recommendation

That City Council authorize the Mayor to execute Amendment No. 2 to the contract with Atkins North America in the amount of $67,409.00 and Amendment No. 3 in the amount of $14,166.13 for additional architectural and engineering services for the VT Mobile Aerospace Engineering project at the Pensacola International Airport. Further that City Council authorize Mayor to take all actions necessary related to the execution of the amendments.

end

body                

 

HEARING REQUIRED:  No Hearing Required

 

SUMMARY:

                                          

Atkins North America was selected as the firm to provide the architectural and engineering design services for the development of the hangar facility to be utilized by VT MAE.  The initial cost negotiated with Atkins for the work was based on a general schematic design developed while formulating the lease agreement with VT MAE.  After commencement of the formal design activity, certain additional services were required.  Additional inspection services were needed to ensure that the concrete for the apron area was being placed in accordance with the required plans and specifications, and additional design services were required to re-design a portion of the second level mezzanine area to include a break area and bathrooms.  As the re-design for the mezzanine was done at the request of VT, they will reimburse the City for the cost. 

 

These items have required Atkins North America to expend additional hours not anticipated in their original fee.  The additional fees have been reviewed by Mott MacDonald as the Program Administrator and deemed to be fair and reasonable.

 

PRIOR ACTION:                     

 

December 17, 2013 - Mayor Ashton Hayward executed a nonbinding Memorandum of Understanding with ST Aerospace which allowed the City to begin contract negotiations.

 

June 13, 2013 - City Council adopted a resolution to support the acceptance of a grant offered by the Florida Department of Transportation as a Joint Participation Agreement # 43360229401 in the amount of $11,090,000 for air commerce park phases I and IA - Infrastructure Development.

 

February 13, 2014 - City Council Discussion Item and Presentation on the ST Aerospace Economic Development Project at the Pensacola International Airport.

 

February 27, 2014 - City Council approved the Interlocal Agreement with Escambia County and the City of Pensacola for Funding of Economic Development Project - ST Aerospace of Mobile, Inc.

 

September 9, 2014 - City Council approved the lease with VT Mobile Aerospace Engineering

 

July 16, 2015 - City Council approved the selection of Greenhut Construction and authorized the Mayor to execute the contract.

 

September 17, 2015 - City Council authorized the Mayor to execute acceptance of the Florida Department of Transportation Joint Participation Agreement # 43571729401 in the amount of $1,531,546 for construction funding to expand the cargo apron and construct a taxiway connector at the Pensacola International Airport of which $1,121,242 will be used towards taxiway connecting future VT MAE facility to runway 17-35.

 

March 17, 2016 - City Council authorized the Mayor to execute acceptance of the Florida Department of Transportation Joint Participation Agreements # 42030029401, # 42960929401, and # 42960939401 in the amount of $2,975,305 for construction of a taxiway connector at the Pensacola International Airport.

 

April 14, 2016 - City Council authorized the Mayor to execute acceptance of the Florida Department of Transportation Joint Participation Agreement # 43571769401 in the amount of $8,599,600 for construction of a hangar at the Pensacola International Airport.

 

September 22, 2016 - City Council authorized the Mayor to execute Amendment No. 1 to the contract with Atkins North America.

 

FUNDING:                     

 

     Budget:                     $23,786,147                     FDOT Grant Entitlements

                                              7,000,000                     Industry Recruitment, Retention, and Expansion Funds

                                              8,000,000                     Interlocal Agreement between City and Escambia County

                                              7,244,300                     VT Mobile Aerospace Engineering, Inc.

                                          $46,030,447

 

      Actual:                     $  2,690,189                     Architectural/Engineering Fees - Design and Construction

                                              1,279,298                     Program Management Fees - Design and Construction

                                                 219,707                     Environmental Assessment

                                                 581,002                     Federal Aviation Administration Equipment Modification

                                                 461,513                     Professional Services

                                                 152,901                     Geotech/Survey/Airport Layout Plan

                                                 150,000                     Construction Manager at Risk Fees - Design

                                                 304,689                     Miscellaneous

                                                 750,000                     Bridge Financing

                                            37,576,696                     Construction Manager at Risk - GMP

                                              1,864,452                     Project Contingency

                                          $46,030,447

 

FINANCIAL IMPACT:

                     

The project is expected to create a minimum of 400 full-time, high skilled jobs with an average salary of $41,000.  The total project cost of $46,030,447 is being funded by a combination of VT MAE investment, state grants, and local funds.  The fees for this amendment will come from a combination of those funds.

 

CITY ATTORNEY REVIEW:    Yes

 1/16/2018

   

STAFF CONTACT:

 

Eric W. Olson, City Administrator

Daniel Flynn, Airport Director

 

ATTACHMENTS:

 

1)                     Amendment No. 2

2)                     Amendment No. 3

 

PRESENTATION:     No   end