City of Pensacola Logo
 
File #: 18-00100    Version: 1 Name:
Type: Legislative Action Item Status: Passed
File created: 2/13/2018 In control: City Council
On agenda: 3/8/2018 Final action: 3/8/2018
Enactment date: Enactment #:
Title: PENSACOLA ENERGY - AWARD OF TASK ORDER 8, NATURAL GAS PIPELINE CONSTRUCTION MISCELLANEOUS WORK
Sponsors: Ashton J. Hayward, III
Attachments: 1. RAW Construction Task Order 8

LEGISLATIVE ACTION ITEM

 

SPONSOR:                         Ashton J. Hayward, III, Mayor

 

SUBJECT:

 

title

PENSACOLA ENERGY - AWARD OF TASK ORDER 8, NATURAL GAS PIPELINE CONSTRUCTION MISCELLANEOUS WORK                       

end

 

RECOMMENDATION:

 

recommendation

That City Council award Task Order 8, Natural Gas Pipeline Construction Miscellaneous Work, to R.A.W. Construction, LLC for $549,300.  Further, that Council authorize Mayor Hayward to execute the task order and take all actions necessary to complete the work.

end

body                

 

HEARING REQUIRED:  No Hearing Required

 

SUMMARY:

                                          

In July 2017, City Council awarded Bid #17-028, Natural Gas Pipeline Construction East of I-110 Low Pressure Area Upgrades, to R.A.W. Construction, LLC. The bid included a unit price option for miscellaneous work, which is for natural gas pipeline maintenance, replacement, and new construction. The Council action included a partial award of $320,058 for the unit price option. Task Order 8 awards $549,300, which is the remainder of the FY 2018 budgeted amount for miscellaneous work.

 

PRIOR ACTION:                     

 

July 13, 2017 - City Council awarded Bid #17-028, Natural Gas Pipeline Construction East of I-110 Low Pressure Area Upgrades for $3,428,485.

 

FUNDING:                     

 

     Budget:                     $ 549,300

 

      Actual:                     $ 549,300

 

FINANCIAL IMPACT:

                     

Funding is available in the Gas Utility Fund from the Florida System Revenue Note, Series 2016.

 

CITY ATTORNEY REVIEW:    Yes

 2/14/2018

   

STAFF CONTACT:

 

Eric W. Olson, City Administrator

Richard Barker, Jr., Chief Financial Officer

Don J. Suarez, Pensacola Energy Director

 

ATTACHMENTS:

 

RAW Construction Task Order 8

 

PRESENTATION:     No   end