File #: 18-00322    Version: 1 Name:
Type: Legislative Action Item Status: Passed
File created: 8/13/2018 In control: City Council
On agenda: 9/13/2018 Final action: 9/13/2018
Enactment date: Enactment #:
Title: PENSACOLA ENERGY - AWARD OF TASK ORDER 1, DEEP TYPE IMPRESSED CURRENT CATHODIC PROTECTION SYSTEM
Sponsors: Ashton J. Hayward, III
Attachments: 1. Bass Engineering Task Order 1

LEGISLATIVE ACTION ITEM

 

SPONSOR:                         Ashton J. Hayward, III, Mayor

 

SUBJECT:

 

title

PENSACOLA ENERGY - AWARD OF TASK ORDER 1, DEEP TYPE IMPRESSED CURRENT CATHODIC PROTECTION SYSTEM                     

end

 

RECOMMENDATION:

 

recommendation

That City Council award Task Order 1, Deep Type Impressed Current Cathodic Protection System (ICCP) located in the Hillview Road area for cathodic protection system improvements on Invitation-to-Bid (ITB) 17-034 - Natural Gas Pipeline Cathodic Protection System Survey and Repair Recommendations, to Bass Engineering Company for $41,230. Further, that Council authorize Mayor Hayward to execute the task order and take all actions necessary to complete the work.

end

body                

 

HEARING REQUIRED:  No Hearing Required

 

SUMMARY:

                                          

In June, 2018, Bass Engineering provided a labor and equipment estimate for the installation of the ICCP system as directed by Pensacola Energy.  Cathodic protection of steel mains minimizes corrosion, and extends the life of the system thereby postponing future infrastructure replacement costs. Task Order 1 will be awarded under the contract’s Extra Work option.

 

PRIOR ACTION:                     

 

August 28, 2017 - The City executed a two-year contract with Bass Engineering, the lowest and most responsible bidder for natural gas pipeline cathodic protections system survey and repair recommendations for $68,740 per year plus an Extra Work option for $87,360 as outlined in the bid specifications.

 

FUNDING:                     

 

     Budget:                     $  87,400

 

      Actual:                     $  41,230

 

FINANCIAL IMPACT:

                     

Funding for installation services is included the Gas Utility Fund Capital budget.

 

CITY ATTORNEY REVIEW:    Yes

 8/15/2018

   

STAFF CONTACT:

 

Keith Wilkins, City Administrator

Richard Barker, Jr., Chief Financial Officer

Don J. Suarez, Pensacola Energy Director

 

ATTACHMENTS:

 

1)                     Bass Engineering Task Order 1

 

PRESENTATION:     No   end