File #: 19-00087    Version: 1 Name:
Type: Legislative Action Item Status: Passed
File created: 2/4/2019 In control: City Council
On agenda: 2/14/2019 Final action: 2/14/2019
Enactment date: Enactment #:
Title: AWARD OF CONTRACT FOR INVITATION TO BID (ITB) #18-037 FLEET MAINTENANCE GARAGE RENOVATION
Sponsors: Grover C. Robinson, IV
Attachments: 1. Tab Sheet, 2. Final Vendor Reference List

LEGISLATIVE ACTION ITEM

 

SPONSOR:                         Grover C. Robinson, IV, Mayor

 

SUBJECT:

 

title

AWARD OF CONTRACT FOR INVITATION TO BID (ITB) #18-037 FLEET MAINTENANCE GARAGE RENOVATION                      

end

 

RECOMMENDATION:

 

recommendation

That City Council award a contract to Vision Construction Ent., Inc. for ITB #18-037 Fleet Maintenance Garage Renovation in the amount of $337,500  plus a 15% contingency of $50,625 for a total amount of $388,125.  Further, that City Council authorize the Mayor to take all actions necessary to execute the contract and complete the project.

end

body                

 

HEARING REQUIRED:  No Hearing Required

 

SUMMARY:

                                          

On September 28, 2018, the City issued an invitation to bid on the Fleet Maintenance Garage Renovation.  This project will consist of demolition work and renovation of the existing building by relocating utilities and modernizing restrooms, relocating the breakroom and office spaces.  This project is necessary to bring the facility into compliance with the Americans with Disabilities Act (ADA), and to modernize the facility for improved efficiency, productivity and occupational health related issues.

 

On November 8, 2018, a total of seven contractors submitted bids; the lowest responsive quote was received from Vision Construction Ent., Inc.  It is recommended that Vision Construction Ent., LLC be awarded the contract with a 15% contingency as recommended by the City’s Public Works & Facilities Department.  The additional contingency is necessary as the facility is nearly fifty years old and there are no detailed drawings or plans available for the building, requiring significant demolition before all modifications and upgrades are fully known.

 

 

PRIOR ACTION:                     

 

None

 

FUNDING:                     

 

     Budget:                     $520,000                      Central Services Fund

 

     Actual:                     $337,500                     Base Bid

                                              50,625                     15% Contingency

                                              33,300                     Architectural & Engineering

    10,000                     Miscellaneous

$431,425

 

 

FINANCIAL IMPACT:

                     

The Fiscal Year 2018 Budget included $170,000 in the Central Services Fund for the renovation of the Garage Facility.  The balance remaining at the end of Fiscal Year 2018 was carried forward to Fiscal Year 2019.  An additional $350,000 was included in the Fiscal Year 2019 Budget for a total budget of $520,000.   To date, $33,430.62 has been spent on this project leaving a balance of $486,569.38 to complete this project.

 

CITY ATTORNEY REVIEW:    Yes

 2/5/2019

   

STAFF CONTACT:

 

Christopher L. Holley, City Administrator

Dennis Fleming, Sanitation Services and Fleet Management Director

 

ATTACHMENTS:

 

1)                     Tab Sheet

2)                     Final Vendor Reference List

 

PRESENTATION:     No   end