City of Pensacola Logo
 
File #: 19-00165    Version: 1 Name:
Type: Legislative Action Item Status: Passed
File created: 3/21/2019 In control: City Council
On agenda: 4/11/2019 Final action: 4/11/2019
Enactment date: Enactment #:
Title: AWARD OF BID #19-014 PENSACOLA INTERNATIONAL AIRPORT ECONOMY LOT 1 EXPANSION PROJECT
Sponsors: Grover C. Robinson, IV
Attachments: 1. Tabulation of Bids, 2. Final Vendor Reference List

LEGISLATIVE ACTION ITEM

 

SPONSOR:                         Grover C. Robinson, IV, Mayor

 

SUBJECT:

 

title

AWARD OF BID #19-014 PENSACOLA INTERNATIONAL AIRPORT ECONOMY LOT 1 EXPANSION PROJECT                     

end

 

RECOMMENDATION:

 

recommendation

That City Council award Bid #19-014 Pensacola International Airport Economy Lot 1 Expansion Project to Panhandle Grading & Paving, Inc., the lowest and most responsible bidder with a base bid of $1,105,801.20 plus a 10% contingency in the amount of $110,580.12 for a total amount of $1,216,381.32.  Further that City Council authorize the Mayor to execute the contract and take all actions necessary to complete the project.

end

body                

 

HEARING REQUIRED:  No Hearing Required

 

SUMMARY:

                                          

The continued strong growth in passenger traffic over the last three years is creating a demand for additional public parking facilities at the main terminal.  The Airport currently has roughly 2800 spaces available for the general public spread among four parking areas.  Airport Staff worked with City Engineering to design a 260 stall expansion to Economy Lot 1.  This project will help meet the immediate short-term parking needs while a longer-term garage expansion project is developed.

 

PRIOR ACTION:                     

 

N/A

 

FUNDING:                     

 

     Budget:                     $ 1,216,900.00

 

      Actual:                     $ 1,105,801.20                     Base Bid

                                                110,580.12                     10% Contingency

                                                       420.00                     Permits

                                          $ 1,216,801.32

 

FINANCIAL IMPACT:

                     

The Fiscal Year 2019 Budget was adopted prior to the completion of the Airport Master Plan.  Addressing the parking issue has become the highest priority from the Master Plan, therefore, some of the capital improvement projects approved in the Fiscal Year 2019 Budget will be delayed and will be funded in later budgets, based on the priority of needs set by the Master Plan.  The funds appropriated for those projects will be shifted to the Economy Lot 1 Expansion Project.

 

CITY ATTORNEY REVIEW:    Yes

 3/27/2019

   

STAFF CONTACT:

 

Christopher L. Holley, City Administrator

Daniel E. Flynn, Airport Director

 

ATTACHMENTS:

 

1)                     Tabulation of Bids

2)                     Final Vendor Reference List

 

PRESENTATION:     No   end