File #: 19-00091    Version: 1 Name:
Type: Legislative Action Item Status: Passed
File created: 2/7/2019 In control: City Council
On agenda: 4/25/2019 Final action: 4/25/2019
Enactment date: Enactment #:
Title: AWARD OF BID #19-012 TEXAR DRIVE 17TH AND 18TH AVENUE OUTFALLS AT BAYOU TEXAR PROJECT
Sponsors: Grover C. Robinson, IV
Attachments: 1. Bid Tabulation, Bid No. 19-012, 2. Final Vender Reference List, Bid No. 19-012, 3. Map, Texar Drive 17th and 18th Avenue Outfalls at Bayou Texar Project

LEGISLATIVE ACTION ITEM

 

SPONSOR:                         Grover C. Robinson, IV, Mayor

 

SUBJECT:

 

title

AWARD OF BID #19-012 TEXAR DRIVE 17TH  AND 18TH AVENUE OUTFALLS AT BAYOU TEXAR PROJECT                     

end

 

RECOMMENDATION:

 

recommendation

That City Council award Bid #19-012 Texar Drive 17th and 18th Avenue Outfalls at Bayou Texar Project to B & W Utilities, Inc., of Pensacola Florida, the lowest and most responsible bidder with a base bid of $299,235.80, plus a 10% contingency in the amount of $29,923.58 for a total amount of $329,159.38.  Further, that City Council authorize the Mayor to execute the contract and take all actions necessary to complete the project.

end

body                

 

HEARING REQUIRED:  No Hearing Required

 

SUMMARY:

                                          

The scope of this project is to provide stormwater treatment for a currently untreated drainage sub-basin within the Bayou Texar Bay Watershed.  This treatment will be provided by installing a proprietary underground treatment unit with associated stormwater structures and piping.  Also, limited localized street flooding will also be addressed in the project area by modifying existing drainage structures and installing new ones, where applicable.  This project is consistent with current technology and industry standards for stormwater retrofit treatment and is part of the City’s ongoing program to improve the water quality of area waterways.

 

PRIOR ACTION:                     

 

None

 

FUNDING:                     

 

     Budget:                     $ 487,700.00                     Stormwater Capital Projects Fund

 

      Actual:                     $ 299,235.80                     Construction Contract

                             29,923.58                     10% Contingency

                             39,527.31                     Engineering Design/Permitting/Surveying

                             25,000.00                     Engineering Management/Inspection (Estimate)

                               5,000.00                     Construction Testing and Misc. (Estimate)

                        $ 398,686.69                     Total 

 

FINANCIAL IMPACT:

                     

The Fiscal Year 2018 Budget appropriated $42,700 for this project and the Fiscal Year 2019 Budget appropriated $445,000 for a total budget amount of $487,700.  To date, $43,263.33 has been expended for completed items related to Surveying, Engineering Design, Studies and Permitting, leaving a remaining balance of $444,436.67.  The remaining budget balance is sufficient to cover the remaining items that have yet to be completed/expended.

 

CITY ATTORNEY REVIEW:    Yes

 4/11/2019

   

STAFF CONTACT:

 

Christopher L. Holley, City Administrator

L. Derrik Owens, Director of Public Works and Facilities/City Engineer

 

ATTACHMENTS:

 

1)                     Bid Tabulation, Bid No. 19-012

2)                     Final Vender Reference List, Bid No. 19-012

3)                     Map, Texar Drive 17th and 18th Avenue Outfalls at Bayou Texar Project

 

PRESENTATION:     No   end