Title: APPROVAL OF REVISED DESIGN PLANS AND CONSTRUCTION TIMELINE FOR HAWKSHAW REDEVELOPMENT (9TH AND ROMANA)
Attachments: 1. Third Amendment to the Declaration of Conditions, Covenants, and Restrictions, 2. Revised Design Plans and Elevations, 3. Third Amendment to Hawkshaw DCRs - Redline 080519

ACTION ITEM

 

SPONSOR:                         Jewel Cannada-Wynn, Chairperson

 

SUBJECT:

 

title

APPROVAL OF REVISED DESIGN PLANS AND CONSTRUCTION TIMELINE FOR HAWKSHAW REDEVELOPMENT (9TH AND ROMANA)                     

end

 

RECOMMENDATION:

 

recommendation

That the Community Redevelopment Agency (CRA) approve the revised design plans for the Hawkshaw redevelopment project at 9th and Romana, as submitted by Hawkshaw Redevelopment Group, LLC.  Further, that the CRA approve the Third Amendment to the Declaration of Conditions, Covenants and Restrictions for the project, eliminating project phasing and extending the timeline for completion.  Finally, that the CRA Chairperson be authorized to execute all necessary documents.

end

body                

 

SUMMARY:

                                          

On June 6, 2017, the Community Redevelopment Agency (CRA) directed NAI Halford to release a Request For Proposals (RFP) for the Hawkshaw site.  After evaluating responses, a Proposal Evaluation Committee recommended selecting Robert Montgomery, LLC as the preferred developer.  The proposal from Mr. Montgomery included construction of thirty-eight (38) residential units, mixed use commercial and multi-family space, the Wine Bar Restaurant and parking.  The project was to be developed in two phases.

 

The new design and development program increases the total residential construction from thirty-eight (38) to no less than fifty (50) residential units.  The Wine Bar shall occupy restaurant and/or retail space in the building on the southwest corner of the property.  The project buildings and structures shall contain approximately 92,000 conditioned square feet, and approximately 132,000 total gross square feet, including conditioned square feet, parking under podium, elevated promenade, exterior corridors and balconies.

 

The project timeline is also revised from two phases to a single phase, with a thirty (30) month completion schedule.  The revised plan complies with the urban design guidelines established for the site in the RFP.

 

PRIOR ACTION:                     

 

November 6, 2017 - CRA approved the development agreement/contract for sale of the Hawkshaw property to Robert Montgomery, LLC.

 

February 26, 2018 - The deed for sale of Hawkshaw property to Hawkshaw Developers, LLC was filed in Escambia County Official Records.

 

June 10, 2019 - CRA granted an extension of the construction commencement deadline for the Hawkshaw project.

 

FUNDING:                     

 

NA

 

FINANCIAL IMPACT:

                     

None.

 

CITY ATTORNEY REVIEW:    Yes

 7/24/2019

   

STAFF CONTACT:

 

M. Helen Gibson, AICP, CRA Administrator

Victoria D’Angelo, Assistant CRA Administrator

 

ATTACHMENTS:

 

 

1)                     Third Amendment to the Declaration of Conditions, Covenants, and Restrictions

2)                     Revised Design Plans and Elevations

 

PRESENTATION:     Yes   end