City of Pensacola Logo
 
File #: 19-00130    Version: 1 Name:
Type: Legislative Action Item Status: Passed
File created: 3/11/2019 In control: City Council
On agenda: 11/14/2019 Final action: 11/14/2019
Enactment date: Enactment #:
Title: AWARD OF BID #19-015 LEE STREET AREA-A HMGP STORMWATER IMPROVEMENT PROJECT
Sponsors: Grover C. Robinson, IV
Attachments: 1. Bid Tabulation, Bid No. 19-015, 2. Final Vendor Reference List, Bid No. 19-015, 3. Map-Lee Street Area A HMGP Stormwater Improvement Project

LEGISLATIVE ACTION ITEM

 

SPONSOR:                         Grover C. Robinson, IV, Mayor

 

SUBJECT:

 

title

AWARD OF BID #19-015 LEE STREET AREA-A HMGP STORMWATER IMPROVEMENT PROJECT                     

end

 

RECOMMENDATION:

 

recommendation

That City Council award Bid #19-015 Lee Street Area-A HMGP Stormwater Improvement Project to Site & Utility, LLC., of Pensacola Florida, the lowest and most responsible bidder with a base bid of $717,936.00 plus a 10% contingency in the amount of $71,793.60 for a total amount of $789,729.60.  Further that City Council authorize the Mayor to execute the contract and take all actions necessary to complete the project.

end

body                

 

HEARING REQUIRED:  No Hearing Required

 

SUMMARY:

                                          

This project will serve as the second construction area (Area A) of the FEMA Hazard Mitigation Grant Program (HMGP) project to provide stormwater drainage improvements at the intersection of West Lee Street and North ‘F’ Street that has been impacted by historical repetitive flooding issues.  More specifically, this final project phase consists of demolishing the three (3) recently purchased residential dwellings along Lee Street and constructing a new stormwater retention pond in the vacated area, along with new underground drainage infrastructure. The completion of the project will significantly reduce roadway and private property flooding in the local area as a result of high intensity rainfall events.

 

PRIOR ACTION:                     

 

October 11, 2018 - Hazard Mitigation Grant Program (HMGP) Grant - Acquisition of Properties Located at 925, 927, and 975 West Lee Street.

 

April 14, 2016 - Award of Contract - Bid #16-022 L Street and Zaragossa Street Stormwater Treatment Enhancement Project.

 

 

FUNDING:                     

 

     Budget:                     $  1,567,485.00                     HMGP Grant Award - Natural Disaster Fund

                                                 322,000.00                     Additional Anticipated HMGP Award

                      $  1,889,485.00                     Total

                                          

      Actual:                     $     717,936.00                     Construction Contract

                                                   71,793.60                     10% Contingency

                                                   25,964.45                     Engineering Design (Completed)

                                                 713,540.08                     L Street and Zaragossa Street (Completed)

                                                 312,235.88                     Acquisition of Properties (Completed)

                                                   25,000.00                     Engineering Management/Inspection (Estimate)

                                                     5,000.00                     Construction Testing and Misc. (Estimate)

                                          $   1,871,470.01                     Total

 

FINANCIAL IMPACT:

                     

Funding for this HMGP Grant Project is appropriated in the Natural Disaster Fund (Areas A and B).  Additional HMGP funding in the amount of $322,000.00 is anticipated to become available once the HMGP Grant Program approves a request to increase the budget due to the bids received being higher than projected in the grant agreement for Phase II of the Construction/Demolition portion of the project for a total amount of $1,889,485.00.  Should the additional anticipated HMGP funding not become available, sufficient funds are available in the Stormwater Capital Projects Fund Stormwater Vaults City-Wide to complete this project.  To date, $1,051,740.41 has been expended for completed items related to Engineering Design, construction of the ‘L’ Street and Zaragossa Street Project (Area B) and the Acquisition of Property located at West Lee Street (Area B) leaving a budgeted balance of $837,744.59.  The remaining budget balance is sufficient to cover the remaining items have yet to be completed/expended.  The additional anticipated HMGP funds will be appropriated on the unencumbered carry forward budget resolution in December.

 

CITY ATTORNEY REVIEW:    Yes

 10/31/2019

   

STAFF CONTACT:

 

Christopher L. Holley, City Administrator

L. Derrik Owens, Director of Public Works and Facilities/City Engineer

 

ATTACHMENTS:

 

1)                     Bid Tabulation, Bid No. 19-015

2)                     Final Vendor Reference List, Bid No. 19-015

3)                     Map - Lee Street Area-A HMGP Stormwater Improvement Project

 

PRESENTATION:     No   end