Title: SPRING STREET PIPE REHABILITATION
Sponsors: Grover C. Robinson, IV
Attachments: 1. Proposal - Spring Street Culvert Rehabilitation, 2. Brochure - Vortex HGAC Buy

LEGISLATIVE ACTION ITEM

 

SPONSOR:                         Grover C. Robinson, IV, Mayor

 

SUBJECT:

 

title

SPRING STREET PIPE REHABILITATION                     

end

 

RECOMMENDATION:

 

recommendation

That City Council award a contract to Vortex Companies of Houston for stormwater system rehabilitation utilizing Houston Galveston Area Co-Operative (HGAC) Contract#TPO7-18 in the amount of $231,284.25 plus a 10% contingency of $23,128.43 for a total amount of $254,412.68. Further, that City Council authorize the Mayor to execute the contract and take all actions necessary to complete the project.

end

body                

 

HEARING REQUIRED:  No Hearing Required

 

SUMMARY:

                                          

This project consists of rehabilitating an existing 36” stormwater pipe and associated underground structures (manholes) located on Spring Street between Wright and Chase Streets. The existing stormwater pipe and manholes are several decades old and in significant disrepair in numerous locations. As a result, the roadway above the pipe and structures has fallen in several times and has become a maintenance and safety issue to traffic. To minimize disruption to the roadway and to expedite the needed repairs, an in-place pipe lining system will be utilized to avoid excavating the roadway to remove and to replace the existing infrastructure in question. This process will ensure the pipe and structure’s longevity for several more decades and will significantly reduce potential public safety issues with the roadway and access to the Downtown Library. The City of Pensacola purchases products and equipment through the Houston Galveston Area Co-Operative (HGAC).  It is a co-operative which procures competitive pricing from multiple vendors for a large variety of industry services.  Vortex Companies offers a Quadex Lining System QLS), which is a propriety system consisting of a geopolymer infused pipe lining product.  Leon County and other Florida municipalities have used the same company under the HGAC contract for similar projects with good results.

 

PRIOR ACTION:                     

 

None

 

FUNDING:                     

 

     Budget:                     $   296,000.00

 

      Actual:                     $   231,284.25  Construction Contract

                             23,128.43  10% Contingency

                               3,469.12  Engineering Design (Completed)

                             30,000.00  Engineering Management/Inspection (Estimate)

                               5,000.00  Construction Testing/Misc. (Estimate)

                                          $   292,881.80  TOTAL 

 

FINANCIAL IMPACT:

                     

This project's total approved budget is $296,000.00 and is funded within the Stormwater Capital Projects Fund.  To date, $3,469.12 has been expended for completed items related to Engineering design and coordination.  The remaining budget balance of $292,530.88 is sufficient to cover the remaining items that have yet to be completed/expended.

 

CITY ATTORNEY REVIEW:    Choose an item.

 1/7/2021

   

STAFF CONTACT:

 

Keith Wilkins, City Administrator

Kerrith Fiddler, Deputy City Administrator - Community Development

L. Derrik Owens, Director of Public Works and Facilities/City Engineer

 