File #: 21-00837    Version: 1 Name:
Type: Legislative Action Item Status: Passed
File created: 9/29/2021 In control: City Council
On agenda: 10/14/2021 Final action: 10/14/2021
Enactment date: Enactment #:
Title: MEMORANDUM OF UNDERSTANDING BETWEEN THE CITY OF PENSACOLA AND CARSON LOVELL COMPANY REGARDING THE PERFORMANCE OF DUE DILIGENCE ON LOTS 4 AND 5 AT THE COMMUNITY MARITIME PARK
Attachments: 1. Memorandum of Understanding between the City of Pensacola and the Carson Lovell Company, 2. TALKING POINTS HAND OUT Presented by Greg Darden, Director of Business Development with Structured Parking Solutions (representing Carson Lovell), 3. LETTER FROM VALENCIA DEV CORP Support for Carson Lovell Company MOU, 4. CLARIFICATION OF LETTER SENT BY VALENCIA DEV CORP, 5. QUALIFYING NOTES HAND OUT Presented by Greg Darden, Director of Business Development with Structured Parking Solutions (representing Carson Lovell)

LEGISLATIVE ACTION ITEM

 

SPONSOR:                         Grover C. Robinson, IV, Mayor

 

SUBJECT:

 

title

MEMORANDUM OF UNDERSTANDING BETWEEN THE CITY OF PENSACOLA AND CARSON LOVELL COMPANY REGARDING THE PERFORMANCE OF DUE DILIGENCE ON LOTS 4 AND 5 AT THE COMMUNITY MARITIME PARK                     

end

 

RECOMMENDATION:

 

recommendation

Staff recommends that City Council reject this Memorandum of Understanding, due to the fact that the City will not receive any income based on what is proposed and the City is potentially at risk to reimburse Carson Lovell their due diligence cost.

end

body                

 

HEARING REQUIRED:  No Hearing Required

 

SUMMARY:

                                          

Pursuant to Florida Statute section 163.380(3)(a), the City issued a public notice of its intent to lease property in the Urban Core Community Redevelopment Area (CRA) and invited proposals from prospective developers.  The lots to be leased are commonly known as Lots 4 and 5 of the Community Maritime Park (CMP). 

 

In July, the City received three proposals and scheduled a special meeting for presentations and discussion. Subsequently, the City Council selected Carson Lovell Company, the 3rd ranked firm, as the developer with whom the Mayor would negotiate a lease.

 

Carson Lovell has proposed the attached Memorandum of Understanding (MOU) that provides a description of the project as “…any combination of municipal parking garage, conference/convention/banquet/museum facility, multifamily rent-targeted dwellings and misc. retail/entertainment space generally located on Parcels 4 and 5.”  The MOU requires the City and Carson Lovell to commit the following timeline:

 

o                     Development Agreement - 60 days from the date of the MOU

o                     Completion of a First Phase Survey - 180 days

o                     City Project Commitment - 45 days after Presentation of the First Phase Survey

 

Deliverables due under the First Phase Survey include the initial architectural masterplan, initial project cost analysis, initial timeline for development, and preliminary financing structure.

 

If the City approves this MOU and then at any point thereafter decides against pursuing the project, the City is agreeing to reimburse Carson Lovell for all costs incurred up to a maximum of $100,000.

 

It is recommended that this MOU not be signed before a preliminary method of financing can be determined, or the City risks incurring a $100,000 expenditure.

 

PRIOR ACTION:                     

 

April 22, 2021 - City Council approved the publication of the public notice for disposition via lease of Lots 4 & 5 at the Community Maritime Park Redevelopment

 

July 12, 2021 - City Council approved the scheduling of a special meeting regarding the redevelopment submitting groups and ranking

 

July 28, 2021 - City Council, at the special meeting, selected Carson Lovell as the developer to be negotiated with

 

FUNDING:                     

 

N/A

 

FINANCIAL IMPACT:

                     

Potential expenditure of up to $100,000 in reimbursement to Carson Lovell for identified costs incurred in completing the first phase study, should the City unilaterally decide not to continue the project.

 

LEGAL REVIEW ONLY BY CITY ATTORNEY:    Yes

 10/4/2021

   

STAFF CONTACT:

 

Kerrith Fiddler, City Administrator

Amy Lovoy, Finance Director

 

ATTACHMENTS:

 

1)                     Memorandum of Understanding between the City of Pensacola and the Carson Lovell Company

 

PRESENTATION:     No   end