City of Pensacola Logo
 
File #: 22-00640    Version: 1 Name:
Type: Legislative Action Item Status: Passed
File created: 5/26/2022 In control: City Council
On agenda: 7/21/2022 Final action: 7/21/2022
Enactment date: Enactment #:
Title: INTERLOCAL AGREEMENT BETWEEN THE CITY OF PENSACOLA AND THE DOWNTOWN IMPROVEMENT BOARD FOR RESTROOM FACILITIES AT MARTIN LUTHER KING JR. PLAZA
Sponsors: Grover C. Robinson, IV
Attachments: 1. Interlocal Agreement, Downtown Improvement Board signed June 28, 2022

LEGISLATIVE ACTION ITEM

 

SPONSOR:                         Grover C. Robinson, IV, Mayor

 

SUBJECT:

 

title

INTERLOCAL AGREEMENT BETWEEN THE CITY OF PENSACOLA AND THE DOWNTOWN IMPROVEMENT BOARD FOR RESTROOM FACILITIES AT MARTIN LUTHER KING JR. PLAZA                     

end

 

RECOMMENDATION:

 

recommendation

That City Council approve an Interlocal Agreement (ILA) with the Downtown Improvement Board (DIB) for the design and construction of two restrooms facilities at Martin Luther King (MLK) Jr. Plaza located at 50 N Palafox Street. Further, that City Council authorize the Mayor to take all actions necessary to negotiate and execute the Interlocal Agreement.

end

body                

 

HEARING REQUIRED:  No Hearing Required

 

SUMMARY:

                                          

With the growth that downtown Pensacola has been experiencing over the past several years, and the increasing popularity of the Saturday market at MLK Jr. Plaza, the City and the DIB desires to enter into an ILA for the design and construction of two restroom facilities to be placed in the plaza. One would be located on the north side of the plaza near Wright Street and the other is to be located on the south side of the plaza near Garden Street. The DIB has agreed to fund up to 50% of the total construction cost of $422,950.

 

PRIOR ACTION:                     

 

May 12, 2022 - City Council approved the transfer of funds within the American Rescue Plan Act (ARPA) Fund.

 

June 28, 2022 - DIB approved the ILA at its June 28, 2022 meeting.

 

 

FUNDING:                     

 

     Budget:                     $211,475 Downtown Improvement Board

                                            211,475 City of Pensacola

                                          $422,950

 

      Actual:                     $211,475 Downtown Improvement Board

                                            211,475 City of Pensacola

                                          $422,950

 

FINANCIAL IMPACT:

                     

Funding in the amount of $225,000 has been appropriated in the American Rescue Plan Act (ARPA) Fund. After execution of the Interlocal Agreement, a Supplemental Budget Resolution will be brought before City Council appropriating $211,475 in the Special Grants Fund to account for DIB’s contributions towards the project. DIB will contribute $89,454 upon execution of the Interlocal and the remaining amount will be paid to the City in monthly installments of $3,390 with the full contribution to be paid within three (3) years of the executed Interlocal.

 

The City will own and operate the facilities and therefore will be responsible for all operating cost, repairs and maintenance estimated to be $60,000 annually.

 

LEGAL REVIEW ONLY BY CITY ATTORNEY:    Yes

 6/30/2022

   

STAFF CONTACT:

 

Kerrith Fiddler, City Administrator

David Forte, Deputy City Administrator - Community Development

Adrian Stills, Parks and Recreation Department Director

 

ATTACHMENTS:

 

1)                     Interlocal Agreement, Downtown Improvement Board signed June 28, 2022

 

PRESENTATION:     No   end