File #: 22-01151    Version: 1 Name:
Type: Legislative Action Item Status: Passed
File created: 11/21/2022 In control: City Council
On agenda: 12/15/2022 Final action: 12/15/2022
Enactment date: Enactment #:
Title: AMENDMENT NO. 1 TO INTERLOCAL AGREEMENT FOR GRANT ADMINISTRATION SERVICES FOR ECONOMIC DEVELOPMENT ADMINISTRATION (EDA) GRANT #04-79-07378 WITH EMERALD COAST REGIONAL PLANNING COUNCIL
Sponsors: D.C. Reeves
Attachments: 1. Interlocal Agreement with Emerald Coast Regional Council EDA Grant 04-79-07378 Management, 2. Amended and Restated Interlocal Agreement with Emerald Coast Regional Council EDA Grant 04-79-07378 Management, 3. Amendment 1 to Amended and Restated Interlocal Agreement Emerald Coast Regional Council EDA Grant 04-79-07378 Management.pdf

LEGISLATIVE ACTION ITEM

 

SPONSOR:                         D.C. Reeves, Mayor

 

SUBJECT:

 

title

AMENDMENT NO. 1 TO INTERLOCAL AGREEMENT FOR GRANT ADMINISTRATION SERVICES FOR ECONOMIC DEVELOPMENT ADMINISTRATION (EDA) GRANT #04-79-07378 WITH EMERALD COAST REGIONAL PLANNING COUNCIL                     

end

 

RECOMMENDATION:

 

recommendation

That City Council approve Amendment No. 1 between the City of Pensacola and Emerald Coast Regional Planning Council.  Further, that City Council authorize the Mayor to take the actions necessary to execute and administer this Amendment, consistent with the terms of the agreement and the Mayor’s Executive Powers as granted in the City Charter.

end

body                

 

HEARING REQUIRED:  No Hearing Required

 

SUMMARY:

                                          

                                          

The Emerald Coast Regional Planning Council (ECRC) assisted the City in developing a Fiscal Year 2018 Public Works and Economic Adjustment Assistance Disaster Supplemental grant application submitted to the U.S. Department of Commerce Economic Development Administration (EDA) during the 2018 grant cycle to help fund the design and construction of Hangar 2 at the Pensacola International Airport.

 

The City was notified on July 18, 2019 that in response to this application, it had been awarded a grant from EDA in the amount of $12,250,000.  On November 14, 2019, City Council authorize the Mayor to execute an Interlocal Agreement between the City and ECRC for Grant Administration Services. Shortly after entering into the Interlocal, the City and ECRC entered into an Amended and Restated Interlocal Agreement (“Restated Agreement “) to add additional terms and conditions to ensure grant compliance.

 

Under the Interlocal, ECRC is to render certain project management, reporting and support services in connection with the EDA grant. The maximum amount payable to ECRC for these services is $35,000 based upon milestones depicting percentage completion of the scope of work. Payments to ECRC will be made from funds provided by EDA.

 

The City and the ECRC have reviewed the progress and agree the services being provided are appropriately continued for the duration of the construction of Hangar 2 or for as long as grant funds remain available to fund the services, whichever occurs sooner, and therefore the parties wish to amend the Restated Agreement to extend the term of the agreement to correspond with the term of the Economic Development Administration (EDA) Grant #04-79-07378.

 

PRIOR ACTION:                     

 

June 13, 2013 - City Council adopted a resolution to support the acceptance of a grant offered by the Florida Department of Transportation as a Joint Participation Agreement # 43360229401 in the amount of $11,090,000 for Air Commerce Park Phases I and IA - Infrastructure Development.

 

February 13, 2014 - City Council Discussion Item and Presentation on the ST Aerospace Economic Development Project at the Pensacola International Airport.

 

February 27, 2014 - City Council approved the Interlocal Agreement with Escambia County and the City of Pensacola for Funding of Economic Development Project - ST Aerospace of Mobile, Inc.

 

September 9, 2014 - City Council approved the lease with VT Mobile Aerospace Engineering.

 

July 16, 2015 - City Council approved the selection of Greenhut Construction and authorized the Mayor to execute the contract.

 

September 17, 2015 - City Council authorized the Mayor to execute acceptance of the Florida Department of Transportation Joint Participation Agreement # 43571729401 in the amount of $1,531,546 for construction funding to expand the cargo apron and construct a taxiway connector at the Pensacola International Airport of which $1,121,242 will be used towards taxiway connecting future VT MAE facility to runway 17-35.

 

March 17, 2016 - City Council authorized the Mayor to execute acceptance of the Florida Department of Transportation Joint Participation Agreements # 42030029401, # 42960929401, and # 42960939401 in the amount of $2,975,305 for construction of a taxiway connector at the Pensacola International Airport.

 

April 14, 2016 - City Council authorized the Mayor to execute acceptance of the Florida Department of Transportation Joint Participation Agreement # 43571769401 in the amount of $8,599,600 for construction of a hangar at the Pensacola International Airport.

 

September 22, 2016 - City Council authorized the Mayor to execute Amendment No. 1 to the lease the VT Mobile Aerospace Engineering.

 

September 22, 2016 - City Council authorized the Mayor to execute Amendment No. 1 to the contract with Atkins North America.

 

February 8, 2017 - City Council authorized the Mayor to execute Amendment No. 2 and Amendment No. 3 to the contract with Atkins North America.

 

March 8, 2018 - City Council authorized the Mayor to execute acceptance of the State of Florida Department of Economic Opportunity Grant Agreement G0009 in the amount of $4,000,000 for construction of infrastructure related to MRO expansion.

 

September 13, 2018 - City Council authorized the Mayor to accept and execute the State of Florida Department of Transportation Public Transportation Grant Agreement Financial Project 441494-2-94-01 in the amount of $3,000,000 for Pensacola International Airport Facilities Development related to MRO expansion.

 

September 13, 2018 - City Council committed funding in the amount of $10 million from Local Option Sales Tax Series IV in support of the aerospace maintenance repair and overhaul (MRO) campus expansion.

 

February 6, 2019 - City Council approved the amended Interlocal Agreement between the Escambia County Board of County Commissioners and the City of Pensacola related to additional funding requirements for the aerospace maintenance, repair, and overhaul (MRO) campus expansion at the Pensacola International Airport, and approved additional Local Option Sales Tax IV funding of $5 million for the City’s share of the aerospace maintenance, repair, and overhaul (MRO) campus expansion at the Pensacola International Airport.

 

March 28, 2019 - City Council authorized the Mayor to accept and execute the Project Development Agreement, the Master Lease of Real Property, the Triumph Grant Award Agreement, and a State of Florida Dept. of Economic Opportunity Grant in the amount of $10,000,000.

 

August 8, 2019 - City Council authorized the Mayor to accept and execute Financial Award No. 04-79-07378 from the U.S. Department of Commerce, Economic Development Administration in the amount of $12,250,000 for the MRO expansion, and authorized the Mayor to accept and execute State of Florida Dept. of Transportation Amendment to the grant agreement for Financial Project 441494-2-94-01 in the amount of $8,000,000 for the MRO expansion.

 

November 14, 2019 - City Council authorize the Mayor to take all necessary action to execute an Interlocal Agreement for Grant Administration Services for the Economic Development Administration (EDA) Grant #04-79-07378 between the Emerald Coast Regional Planning Council and the City of Pensacola.

 

January 16, 2020 - City Council approved the selection of Brasfield & Gorrie, LLC, as the Construction Manager at Risk for Hangar 2 and authorized the Mayor to execute the contract.

 

March 26, 2020 - City Council authorized the Mayor to execute acceptance of the State of Florida Department of Economic Opportunity Florida Job Growth Infrastructure Grant

Agreement in the amount of $4,875,000 related to the MRO aviation campus expansion project.

 

July 16, 2020 - City Council authorized the Mayor to accept and execute the State of Florida Department. of Transportation Amendment to the grant agreement for Financial Project 441494-2-94-01 in the amount of $34,000,000 for the MRO expansion.

 

August 10, 2020 - City Council approved Resolution 2020-18 related to the State of Florida Department of Transportation Amendment to the grant agreement for Financial Project 441494-2-94-01 in the amount of $34,000,000 for the MRO expansion.

 

November 12, 2020 - City Council approved Amendment No. 1 to Construction Manager At Risk Contact between the City and Brasfield & Gorrie, LLC (The ‘GMP Amendment’) for Hangar 2 of Project Titan/MRO Campus at Pensacola International Airport.

 

August 12, 2021 - City Council authorized the Mayor to accept and execute the State of Florida Department. of Transportation Amendment to the grant agreement for Financial Project 441494-2-94-01 in the amount of $1,000,000 for the MRO expansion.

 

August 18, 2022 - City Council authorized the Mayor to accept and execute the State of Florida Department. of Transportation Amendment to the grant agreement for Financial Project 441494-2-94-01 in the amount of $2,000,000 for the MRO expansion.

 

FUNDING:                     

 

Budget:                     $   35,000,000   ST Aerospace Engineering

                                                 3,000,000   State Legislature

                                               14,000,000   Governor’s Job Growth

                                               45,000,000   FDOT Grant

                                               15,000,000   Escambia County

                                               15,000,000   City Local Option Sales Tax Series IV

                                               12,250,000   Federal - U.S. Economic Development Administration

                                               66,000,000   Triumph Gulf Coast

                                                 4,875,000   Florida DEO Grant

                                          $ 210,125,000

 

      Actual:                     $ 210,125,000

 

 

FINANCIAL IMPACT:

                     

Payments to ECRC will be made from funds provided by EDA. The funds for the project were appropriated in the Airport Fund on Supplemental Budget Resolution No. 2019-13 at the March 28, 2019 City Council Meeting.

 

LEGAL REVIEW ONLY BY CITY ATTORNEY:    Yes

 12/1/2022

   

STAFF CONTACT:

 

Kerrith Fiddler, City Administrator

Amy Miller, Deputy City Administrator - Administration & Enterprise

Matthew F. Coughlin, Airport Director

 

ATTACHMENTS:

 

1)                     Interlocal Agreement with Emerald Coast Regional Council EDA Grant 04-79-07378 Management

2)                     Amended and Restated Interlocal Agreement with Emerald Coast Regional Council EDA Grant 04-79-07378 Management

3)                     Amendment 1 to Amended and Restated Interlocal Agreement Emerald Coast Regional Council EDA Grant 04-79-07378 Management

 

PRESENTATION:     No   end